Construction Photo
Album
Welcome!
Construction is well underway on the Hoover Dam Bypass Project: both the
Arizona and the Nevada Approaches are finished and construction on the Colorado River Bridge is steadily
progressing! Scroll down the page (or use the Quick Jump menu)
to see the most recent construction photos. As construction
continues, this page will be updated periodically to give you a quick
peek at the progress and on-going activities at the construction
site.
Click on any
thumbnail to view an enlarged
version of that photo.
Please note that you will need to use the Back button on your
browser to return to this page. If you prefer a higher
resolution image (300 dpi or more), you can also download these from
our site using the High Resolution link located below
each thumbnail. Please note that these higher resolution
images (which are provided in TIF format) will take longer to
download.
Quick Jump:
|
|
2010 Photos |
|
|
June/July 2010 |
April 2010 |
January 2010 |
|
May 2010 |
March 2010 |
February 2010 |
|
2009 Photos |
|
|
December 2009 |
|
April 2009 |
|
November 2009 |
August 2009 |
March 2009 |
|
October 2009 |
June 2009 |
February 2009 |
|
September 2009 |
May 2009 |
January 2009 |
|
2008 Photos |
|
|
December 2008 |
|
|
|
November 2008 |
June 2008 |
Interim Surfacing March '08 |
|
October 2008 |
Interim Surfacing May '08 |
March 2008 |
|
September 2008 |
May 2008 |
Interim Surfacing Feb '08 |
|
August 2008 |
Interim Surfacing April '08 |
February 2008 |
|
July 2008 |
April 2008 |
January 2008 |
|
2007 Photos |
|
|
December 2007 |
July 2007 |
|
|
November 2007 |
June 2007 |
March 2007 |
|
September/October 2007 |
May 2007 |
February 2007 |
|
August 2007 |
April 2007 |
January 2007 |
|
2006 Photos |
|
|
|
August 2006 |
April 2006 |
|
November/December 2006 |
July 2006 |
March 2006 |
|
October 2006 |
June 2006 |
February 2006 |
|
September 2006 |
May 2006 |
January 2006 |
|
2005 Photos |
|
|
December 2005 |
August 2005 |
April 2005 |
|
November 2005 |
July 2005 |
March 2005 |
|
October 2005 |
June 2005 |
February 2005 |
|
September 2005 |
May 2005 |
January 2005 |
|
|
Additional Images/Photos (Including
Arizona Approach and the live webcam.) |
|
|
|
Images from June & July 2010 |
|
Colorado River Bridge...
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|
.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from May 2010 |
|
Colorado River Bridge...
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from April 2010 |
|
Colorado River Bridge...
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from March 2010 |
|
Colorado River Bridge...
|

looking southeast
View of the bridge as seen from Nevada towards Arizona.
In the background, the Arizona approach roadway is visible.
High Resolution TIF (14 MB) |

looking south
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) and the new US93 alignment as seen from above Hoover Dam.
The Arch is complete with all spandrel piers constructed. Steel
girders remain to be placed for spans 6 and 7 and portion of span
14. Stay-in-place steel decking is erected between the girders at
spans 10 and 11. Climbing scaffolding is attached to pier 6-RT
column.
High Resolution TIF (14 MB)
|

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge).
Left side of the picture – Steel girders are staged on the approach
deck, waiting to be set between the Arch spandrel piers.
Stay-in-place steel decking is erected between the girders at spans
10 and 11.
Right side of the picture – A mobile crane is set on the deck,
servicing workers below at the AZ skewback footing.
High Resolution TIF (14 MB) |

looking north
View of the bridge as seen from Nevada towards Arizona.
Steel girders are staged on the Nevada approach deck, waiting to be
set between the Arch spandrel piers. Stay-in-place steel decking is
erected between the girders at spans 10 and 11.
In the background, the Arizona approach roadway is visible.
High Resolution TIF (14 MB)
|

High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from February 2010 |
|
Colorado River Bridge...
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

.
High Resolution TIF (14 MB) |

.
High Resolution TIF (14 MB)
|

.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from January 2010 |
|
Colorado River Bridge...
|

looking east
A truck transports a 115’ long steel girder onto the NV approach and
waits for off loading. Attached to the top flanges of the girder,
above the end plate, are temporary support brackets the will suspend
the girder in-place from the top of the pier cap until PT bars are
installed through the holes in the end plate and attach the girder
to the pier cap face.
High Resolution TIF (14 MB) |

looking west
In the Obayashi / PSM, JV precast yard located near Boulder City,
workers utilize a rubber tire gantry crane to hoist a 115’ long
steel girder onto a truck for transport to the bridge site.
High Resolution TIF (14 MB)
|

looking east
The North highline hoists and transports a steel girder out onto the
Arch for placement between Pier 10 and 11 spandrel column pier caps.
On the NV approach deck, several girders are stage for sequenced
placement. The South highline is in use, delivering materials to
waiting crews on the Arch. To the bottom left of the picture, the
orange stripping platform is cantilevered over the completed right
barrier railing to allow worker access to the underside of the deck.
Across the canyon, a Grove RT635C Crane sets on the AZ approach
deck, above Pier 14, servicing crews working below on the AZ
skewback.
High Resolution TIF (14 MB) |

looking northeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from downstream of the Hoover Dam.
On the Nevada approach, piers 3, 4, and 5 are visible. On the Arch,
all spandrel piers are completed with climbing scaffolding attached
to piers 6-LT\RT and 13-LT columns. Pier 13-RT column has system
scaffolding encasing it for worker access.
The north highline crane transports a steel girder out for erection
between Pier 10 and 11 spandrel column pier caps. The South highline
is returning after delivering crews to work areas on the Arch.
High Resolution TIF (14 MB)
|

looking north
Parked partially on the bridge deck at span 1, Olsen Beal crews
attach highline crane rigging and prepare a steel girder for off
loading. Safety lines have been installed to the tops of the web
flanges. Temporary support brackets will be attached to web flanges
above the end plates prior to setting this girder into its final
position between two spandrel column pier caps.
High Resolution TIF (14 MB) |

looking southeast
As seen from the existing US93 Hairpin in Nevada, the completed Arch
spans across the Colorado River.
From right to left side of the picture – Spandrel Pier 6 is
visible with climbing scaffolding attached to the left & right
columns. Piers 7 through 13 are completed with pier caps in place.
Steel girders spanning between pier 9 and 10 (span 10) and between
10 and 11 (span11) are erected with access scaffolding visible,
suspended from the pier caps.
Spanning the canyon above the bridge are the twin cables of the
highline crane systems.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from December 2009 |
|
Colorado River Bridge...
|

looking south
View of two of four steel girders, set in place, spanning between
piers 9 and 10. Suspended from the top of the piers caps, are
temporary platforms to allow worker access for steel girder
placement.
Utilizing the cantilevered man basket, suspended from the south
highline, Obayashi / PSM, JV crews access the underside of the right
Arch rib below pier 10 to perform finishing work of the Arch soffit.
High Resolution TIF (14 MB) |

looking north
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from downstream of the Hoover Dam.
On the Nevada approach, piers 3, 4, and 5 are visible. On the Arch,
Spandrel Piers 6 through 13 are completed with their caps spanning
between the left and right columns. Two of four steel girders span
between piers 9 and 10. Utilizing the cantilevered man basket,
suspended from the south highline, Obayashi / PSM, JV crews access
the underside of the right Arch rib to perform finishing work.
High Resolution TIF (14 MB)
|

looking southeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from existing US93 hairpin in Nevada.
Left to Right side of the picture – The
completed Arizona approach with the deck constructed to Pier 14.
Climbing scaffolding is attached to Pier 13-LT. Obayashi / PSM, JV
crews remove system scaffolding from Pier 13-RT. Completed pier caps
are visible for piers 13, 12, 11, 10, and 9 with temporary access
platforms attached. Moveable access platforms ride the top of the
Arch between piers 11 and 12 for finishing operations. Below the
right arch rib, a cantilevered man basket is suspended from the
south highline to allow finishing operations of the Arch soffit.
High Resolution TIF (14 MB) |

looking northwest
On the Nevada approach deck, steel girders are staged with steel
safety lines attached along the top of the upper flange. These
girders, weighing upwards of 50 tons will be transported by the
highline crane and placed to span between the spandrel pier caps, on
top of which, the concrete roadway deck will be constructed.
High Resolution TIF (14 MB) |

looking south
On the Nevada approach deck, Obayashi / PSM, JV crews place concrete
to construct the southbound right side barrier railing.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from the right of Abutment 1 in Nevada.
Left side of the picture – The completed Nevada
approach with the deck constructed to Pier 5. Obayashi / PSM, JV
crews continue constructing the southbound right side barrier
railing. Steel girders are staged on the deck, awaiting placement
between spandrel piers.
Right side of the picture – all spandrel piers and
pier caps are completed. Scaffolding encases piers 6, 7, and 13.
Temporary platforms are suspended from the tops of the piers caps to
allow worker access for steel girder placement.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from November 2009 |
|
Colorado River Bridge...
|

looking north
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from downstream of the Hoover Dam.
On the Nevada approach, piers 2, 3, 4, and 5 are visible. On the
Arch, Pier 6 is erected to segment 13, Piers 7, 8, 9, 10, 11 and 12
are completed with the falsework for their pier caps spanning
between the left and right columns, and Pier 13 is completed with
the climbing scaffolding attached at the bottom of the left column.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from the right of Abutment 1 in Nevada.
Left side of the picture – The completed Nevada
approach with the deck constructed to Pier 5. Obayashi / PSM, JV
crews construct formwork for the southbound right side barrier
railing.
Right side of the picture – all spandrel piers are
completed with the exception of Pier 6. Falsework and formwork for
Piers 7 and 12 spans between their left and right columns. Caps at
Piers 8, 9, 10, and 11 are completed and formwork removed.
High Resolution TIF (14 MB) |

looking southeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from the deck at Pier 5.
Spandrel Pier 6-right is erected to segment 18, Pier 6-left to
segment 16. Utilizing the highline, Olsen Beal crews are transported
off of Pier 6-left in a man basket. Pier 6-right is completed with
its 18th segment set. Further out on the Arch, Pier 7 is completed
with the falsework and formwork for the pier cap in place. Spanning
between the left and right ribs of the Arch at each pier, precast
concrete panels encase the steel strut members.
High Resolution TIF (14 MB) |

looking southwest
As seen from the existing US93 Hairpin in Nevada, the completed Arch
spans across the Colorado River.
From right to left side of the picture – Spandrel Pier 6-right is
erected to segment 18, Pier 6-left to segment 16. Pier 7 is
completed with the falsework and formwork for the pier cap in place.
Caps at Piers 8, 9, 10 and 11 are completed with their formwork
stripped. Falsework and formwork for Pier 12’s cap is set.
Spanning the canyon above the bridge are the twin cables of the
highline crane system.
High Resolution TIF (14 MB) |

looking northwest
On the Nevada approach, Obayashi / PSM, JV crews set formwork for
the southbound right side barrier railing. A Quality Control field
engineer inspects the operation.
High Resolution TIF (14 MB) |

looking west
Underside view of the bridge as seen from the existing US93 at the
Nevada Hairpin. Utilizing an under slung mobile scaffolding,
Obayashi / PSM, JV crews remove deck overhang brackets from spans 1
and 2. High above the deck, the highline cranes transport materials
out to the Arch.
High Resolution TIF (14 MB) |

looking south
The Arizona Approach as viewed from the Hoover Dam parking lot in
Arizona.
From left to right side of the picture – the completed
deck and Pier 14. Pier 13 is completed, awaiting placement of pier
cap falsework. Piers 12 and 11 are completed with formwork and
falsework in place for the caps. Scaffolding encases the columns of
Piers 11, 12, and 13-left for worker access. At the far right, the
cap of Pier 10 is visible above the Arch. A temporary access bridge
spans between the skewback footing of Pier 14 and the Arch at Pier
13.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from October 2009 |
|
Colorado River Bridge...
|

looking southwest
On the Arizona approach, Olsen Beal crews remove the temporary
pylons from above Pier 14 using a Liebherr LTM1400-7.1 crane.
Right Center of the picture – Utilizing the highline
crane, Olsen Beal crews erect segment 5 of Pier 11-left.
High Resolution TIF (14 MB) |

looking north
On the Nevada approach, Obayashi / PSM, JV crews assemble pier cap
falsework and formwork.
High Resolution TIF (14 MB) |

looking south
On the Nevada approach, a delivered precast spandrel column segment
waits to be transported out onto the Arch by the highline crane
system. Crews attach temporary platforms to the sides of the
segments for worker access. Steel post tensioning rods are
pre-loaded into the vertical ducts in the segment walls along with a
survey prism, attached to the upper portion of this segment prior to
transportation.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from the right side of abutment 1.
Left side of the picture – The completed Nevada
approach, with piers 4 and 5 visible.
Center to Right side of the picture – Pier 7 is
erected to segment 3. Piers 8, 9, 10, and 11 are complete and have
cap falsework in place. Between the two Arch ribs, the steel struts
are encased in pre-cast concrete panels.
High Resolution TIF (14 MB) |

looking northeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from downstream of the Hoover Dam.
On the Nevada approach, piers 3, 4, and 5 are visible. On the Arch,
spandrel columns are completed at Piers 8, 9, 10, and 11 with the
falsework for their pier caps spanning between the left and right
columns. Pier 7 is erected to segment 4, Pier 12-left to segment 7
and Pier 12-right to segment 10.
High Resolution TIF (14 MB) |

looking south
Left side of the picture – Utilizing the highline crane, Olsen Beal
crews erect segment 2 of Pier 13-right. Pier 13-left has segment 1
erected on top of the plinth. To the left of Pier 13, an access
bridge spans between the Arch and Pier 14
Right side of the picture – Pier 12-right is erected to segment 9
while Pier12-left to segment 7.
High Resolution TIF (14 MB) |

looking southwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from Arizona, looking towards Nevada.
Left side of the picture – The pier cap falsework is
erected on top of Piers 8, 9, and 10. Olsen Beal crews continue
erecting precast concrete spandrel pier column segments at Pier 7.
Right Center of the picture – the completed Nevada
approach is visible.
High Resolution TIF (14 MB) |

looking west
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from above the left side of abutment 2, facing Nevada.
Left side of the picture – The completed Arizona
approach and Pier 14.
Center to Right side of the picture – The completed
Arch with spandrel columns in various stages of completion. Pier
13-left has segment 1 erected, Pier 12-right is erected to segment
10, Pier 12-left to segment 7, Pier 11 is complete with the cap
falsework spanning between the columns. Behind Pier 11, completed
Piers 10, 9, and 8 are visible. The steel struts between the two
Arch ribs are encased in pre-cast concrete panels.
High Resolution TIF (14 MB) |

looking southeast
As seen from the existing US93 Hairpin in Nevada, the completed Arch
spans the Colorado River.
Formwork for Pier 6 plinths are in place. Pier 7 is erected to
segment 3; Piers 8, 9, 10, and 11 are complete and have cap
falsework in place. Between the two Arch ribs, pre-cast concrete
panels encase the steel struts.
High Resolution TIF (14 MB) |

looking northeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from the right side of abutment 1.
Right Center of the picture – The Arch is complete. An
Arch strut is erected between the ribs at Pier 6 and precast
concrete spandrel pier column segments at erected at Pier 7.
Left Center of the picture – On the Nevada approach,
pier cap falsework is being constructed.
High Resolution TIF (14 MB) |

looking west
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from above the left side of abutment 2, facing Nevada.
On the Arch, Olsen Beal crews are erecting precast concrete spandrel
pier segments at Piers 7, 8, 9, 10, 11, and 12. Temporary platforms
are attached to the sides of the segments for worker access.
On the Nevada approach, pier cap falsework is being constructed.
Once finished, they will be transported out and attached to, and
span between, the completed pier columns.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from September 2009 |
|
Colorado River Bridge...
|

looking southwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from Hoover Dam.
The Arch is completed with a majority of the temporary forestays and
backstays removed. The temporary pylons for the cable stays remain
standing on top of Pier 5 (Nevada) and 14 (Arizona). Utilizing the
highline crane, Obayashi / PSM, JV crews remove work platforms from
on top of Arizona pylons.
High Resolution TIF (14 MB) |

looking west
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from the left side of abutment 2, facing Nevada.
The Arch is completed with a majority of the temporary stays
removed. Obayashi / PSM, JV crews are installing the precast
concrete panels around the Arch strut at Pier 11. Formwork is set
for construction of the spandrel column plinths at Piers 10, 11, 12,
and 13.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from the right side of abutment 1 with a majority of the
temporary stays removed. Obayashi / PSM, JV crews are in the process
of removing the remaining stays and temporary pylons. On the Arch,
work is progressing to construct the plinths for the spandrel
columns and installation of the precast concrete panels around the
Arch struts.
High Resolution TIF (14 MB) |

looking southeast
Obayashi / PSM, JV crews removing the stay cables from the temporary
pylons on the Nevada approach, above Pier 5.
High Resolution TIF (14 MB) |

looking southeast
Obayashi / PSM, JV crews removing the stay cables from the temporary
pylons on the Nevada approach, above Pier 5.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike
O'Callaghan-Pat Tillman Memorial Bridge) from the right side of
abutment 1.
Left side of the picture –
Olsen Beal crews continue removal of the temporary pylons from above
Pier 5 using a Liebherr LTM1400-7.1 crane.
Right Center of the picture –
the completed Arch with precast spandrel column segments erected at
Piers 8-LT\RT, 9-LT, 10-LT, and 11-LT\RT. Crews are at Pier 10-RT
waiting for the highline to deliver its first segment.
High Resolution TIF (14 MB) |

looking north
Using a crawler crane, Olsen Beal crews unload a precast Spandrel
column segment and prepare it for transport to Pier 10 by the
highline crane. The segment has work scaffolding attached to the
exterior sides and vertical post tensioning bars inserted into the
ducts.
High Resolution TIF (14 MB) |

looking east
Left side of the picture – on the Nevada approach, above Pier
5, Olsen Beal crews continue removal of the temporary pylons using a
Liebherr LTM1400-7.1 crane.
Center of the picture – the south highline crane carries a
precast Spandrel column segment out for erection at Pier 10.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from August 2009 |

View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) as seen from along side of Abutment 2 in Arizona.
The Nevada and Arizona Arch cantilevers are constructed to segment 26 with the closure segment remaining to be constructed. The temporary stay system is complete with all the forestay/backstays installed.
Spanning between the two ribs of the Arch are the Arch struts (grey steel X structures), connecting the ribs together.
At the right side of the picture, the Nevada approach is visible.
Spanning the canyon, above the temporary pylon is the highline crane system.
High Resolution TIF (14 MB) |

Left side of the picture – The Arizona Arch headings are constructed out to segment 26 with all the forestays installed. Spanning between the two ribs is a temporary strut which will be kept in place until the permanent Arch strut is erected at segment 24.
Right side of the picture - The Nevada Arch headings are constructed out to segment 26 with all the forestays installed and the permanent Arch strut erected at segments 19 & 24.
High Resolution TIF (14 MB) |

View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from below. The Arch cantilevers are nearing connection with the closure segment remaining to be constructed.
Left side of the picture – The Nevada Arch cantilevers are constructed out to segment 26. Arch struts are erected between the ribs at segments 19 & 24.
Right side of the picture - The Arizona Arch headings are constructed out to segment 26. An Arch strut is erected between the ribs at segments 19, with a temporary strut at segment 23
High Resolution TIF (14 MB) |

View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from Hoover Dam.
The Nevada and Arizona Arch cantilevers are constructed to segment 26 with the closure segment remaining to be constructed.
The temporary pylons for the cable stays are constructed on top of Pier 5 in Nevada with all the Forestay/backstays installed.
Arch struts (grey steel X structures), connecting the two Arch ribs, are constructed at Nevada segments 7, 13, 19, and 24. On top of the Arch ribs, at these locations, precast column segments for the spandrel piers will be erected.
High Resolution TIF (14 MB) |

View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from downstream of the Hoover Dam.
Left side of the picture – The Nevada approach is visible with the Arch headings projecting outward to segment 26 with all Stay systems installed.
Right side of the picture - The Arizona approach is visible with the Arch headings projecting outward to segment 26 with all Stay systems installed.
High Resolution TIF (14 MB) |

Left side of the picture – The Arizona Arch headings are constructed out to segment 26 with all the forestays installed. Spanning between the two ribs is a temporary strut which will be kept in place until the permanent Arch strut is erected at segment 24.
Right side of the picture - The Nevada Arch headings are constructed out to segment 26 with all the forestays installed and the permanent Arch strut erected at segment 24.
Obayashi / PSM, JV crews are currently constructing formwork for the closure segment to complete the connection between the Nevada and Arizona cantilevers.
High Resolution TIF (14 MB) |

View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial Bridge) from downstream of the Hoover Dam.
Both ribs of the Arch are constructed to segment 26 with the form travelers removed. Stay system installation is completed. At the center of the Arch, light can be seen coming from the interior of the Arch ribs, shining through the gap between the Nevada and Arizona cantilevers.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from June 2009 |
|
Colorado River Bridge...
|

looking southwest
View of the Arizona approach of the CO River Bridge (Mike
O'Callaghan-Pat Tillman Memorial Bridge).
The temporary pylons for the cable stays are constructed on top of
Pier 14. The Arch projects outward to segment 22 with forestay
cables spanning between the pylons and the Arch. Backstays span
between the temporary pylon and the backstay anchor block.
Arch struts (grey steel X structures), connecting the two Arch ribs,
are constructed at Arizona segments 7, 13, and 19. On top of the
Arch ribs, at these locations, precast column segments for the
spandrel piers will be erected.
Forestays 11 are installed into the temporary pylon heads, waiting
installation into the Arch ribs at segments 22. Backstays F are
fabricated on the Arizona approach and await installation.
High Resolution TIF (14 MB) |

looking northeast
View of the Nevada approach of the CO River Bridge (Mike
O'Callaghan-Pat Tillman Memorial Bridge).
The temporary pylons for the cable stays are constructed on top of
Pier 5. The Arch projects outward to segment 22 with forestay cables
spanning between the pylons and the Arch. Backstays span between the
temporary pylon and the backstay anchor block.
Arch struts (grey steel X structures), connecting the two Arch ribs,
are constructed at Nevada segments 7, 13, and 19. On top of the Arch
ribs, at these locations, precast column segments for the spandrel
piers will be erected.
High Resolution TIF (14 MB) |

looking southwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from above Hoover Dam.
Left side of the picture – The Arizona approach is
visible with the Arch headings projecting outward to segment 23.
Right side of the picture - The Nevada approach is
visible with the Arch headings projecting outward to segment 22.
High Resolution TIF (14 MB) |

looking northeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from downstream of the Hoover Dam.
Left side of the picture – In Nevada, both ribs of the
Arch are constructed to segment 22. The form travelers are launched
out to segment 23 with forestays installed to segment 20.
Right side of the picture - In Arizona, both ribs of
the Arch are constructed to segment 22. The left form traveler is
launched out to segment 23 with forestays installed to segment 20.
High Resolution TIF (14 MB) |

looking northeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) with Hoover Dam and Lake Mead in the background.
High Resolution TIF (14 MB) |

looking south
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge).
Left side of the picture – The Arizona approach alignment along with
the Kingman Wash interchange and the Sugar Loaf Mountain Bridge.
Right side of the picture - The construction office complex situated
in the future Pedestrian Plaza parking lot. The almost complete
pedestrian access ramp zigzags up the mountain side from the office
area to the bridge abutment 1.
High Resolution TIF (14 MB) |

looking southwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) and the new US93 alignment as seen from above Hoover Dam.
Lower Left to top right of the picture – The current
US93 alignment winds from Arizona, across Hoover Dam, and on into
Nevada.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from May 2009 |
|
Colorado River Bridge...
|

looking southeast
In the foreground, an Obayashi / PSM, JV worker and QC engineer
place imbeds and adjust reinforcing steel in preparation for top
slab exterior formwork to be set on segment NV22-LT in Nevada.
In the background, the left and right Arch ribs project outward from
the AZ skewback footing.
High Resolution TIF (14 MB) |

looking southeast
View of the left / right Arch ribs as they project outward from the
AZ skewback footing. The outer form of the form traveler on the left
rib is launched out to segment 22 and is waiting for the reinforcing
steel cage to be set. The form traveler on the right rib is
currently at segment 21 and crews are removing the top slab exterior
formwork and preparing for the collapsing of the inner core
formwork. The south highline crane is being rigged to the formwork
preparing for removal.
The forestays are visible, spanning from the temporary pylon above
Pier 14 and connecting to the Arch.
High Resolution TIF (14 MB) |

looking northeast
Arch segment NV19-LT diaphragm / arch strut post-tensioning blister
formwork prior to concrete placement as viewed from inside the
Nevada right arch rib. To the left and right, the temporary forestay
blister can be seen as constructed alongside the Arch interior wall.
Below the blisters are blockouts in the floor slab where the
temporary strut will be attached to the underside of the Arch with
post tensioning bars.
High Resolution TIF (14 MB) |

looking north
Working within the confines of a temporary platform at the Pier 8
Arch strut and outfitted with personal fall protection equipment,
Obayashi / PSM, JV personnel set blockouts for the transverse
post-tensioning bars that will attach the strut, connecting the left
and right arch ribs.
On top of the Arch rib, to the right, a template that holds the
vertical post-tensioning bars where the pier 8 right column is to be
erected can be seen. Connected to the exterior of the Arch and
wrapped in white Burlene, is the concrete supply pipe, spanning
between the stationary concrete pump at the NV hairpin and the
placing boom. Access to the strut is provided through the round
access hatch in the Arch wall.
High Resolution TIF (14 MB) |

looking northwest
Looking back station down the exterior of the right arch rib in
Nevada at the forestays as they project downward from the temporary
pylons erected on top of pier 5. In the foreground, a template holds
the vertical post-tensioning bars where the pier 8 south column is
to be erected. To the right, Obayashi / PSM, JV personnel, outfitted
with personal fall protection equipment, work within the confines of
a temporary platform, stripping formwork and preparing for the arch
strut placement.
High Resolution TIF (14 MB) |

looking north
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from downstream of the Hoover Dam.
Left side of the picture – In Nevada, the right rib of
the Arch is constructed to segment 21 and the form traveler is
launched out to segment 22 on the left rib. Crews are currently
installing forestays to segment 22 and backstays to the backstay
anchor block on the NV approach.
Right side of the picture – The Arch, constructed to
segment 21, from the AZ skewback. A temporary bridge spanning
between Pier 14 and the Arch can bee seen. This allows simplified
construction worker access to the Arch from the Arizona approach
area.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from April 2009 |
|
Colorado River Bridge...
|

looking south
View of the Arch as seen from the existing US93 at the Nevada
hairpin.
Left side of the picture – The right and left Arch
ribs cantilever from the AZ skewback out to segment 17. A temporary
work platform spans between the ribs at segment 13 to allow for
installation of the steel strut.
Right side of the picture – The Arch cantilevers out
to segment 19 in NV. The temporary forestay cables support the Arch
until Arch completion. Crews are in the process of installing
forestays into the Arch behind the form traveler system. A stairway
system is attached to the outside of the Arch for access to the form
travelers.
High Resolution TIF (14 MB) |

looking north
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from downstream of the Hoover Dam.
Left side of the picture – The Arch, constructed to
segment 19 from the NV skewback. Crews are in the process of
installing forestays into the Arch behind the form traveler system.
Right side of the picture – The Arch, constructed to
segment 17, from the AZ skewback.
At the leading edge of the Arch cantilevers, crews continue to
advance the form travelers and construct Arch segments.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from the right of Abutment 1 in Nevada.
Left side of the picture – The completed Nevada
approach with the temporary pylons for the cable stays constructed
on top of Pier 5. The Arch projects outward to segment 19 with
forestay cables spanning between the pylons and the Arch.
Right side of the picture – The completed Arizona
approach with the temporary pylons for the cable stays constructed
on top of Pier 14. The Arch projects outward to segment 17 with
forestay cables spanning between the pylons and the Arch.
Spanning the canyon overhead are the twin cableway cranes.
High Resolution TIF (14 MB) |

looking west
At the south back stay anchor block in Arizona, an Obayashi / PSM,
JV crew utilize hydraulic post-tensioning jacks to simultaneously
stress a set of back stays. These stays span between the anchor
block and the temporary pylon head above Pier 14.
High Resolution TIF (14 MB) |

looking southwest
On top of the South temporary pylon above Pier 14 in Arizona, an
Obayashi / PSM, JV crew position hydraulic post-tensioning jacks in
preparation of stressing of a set of forestays connected to the
Arch. These cables span between the temporary pylon head above Pier
14 and the arch.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from March 2009 |
|
Colorado River Bridge...
|

looking southwest
Nevada Approach and Arch headings as viewed from the crest of Hoover
Dam. The left and right ribs of the Arch are constructed out to
segment 16. Six sets of forestay cables span from the Arch ribs to
the temporary pylons heads and Six sets of backstays span between
the head and the backstay anchor block.
Between the Arch ribs are the steel Strut assemblies, located where
spandrel Piers columns 6 and 7 will be erected.
High Resolution TIF (14 MB) |

looking southeast
As seen from the existing US93 Hairpin in Nevada, the left and right
Arch ribs project outwards over the Colorado River. Forestay cables
span from the Arch ribs to the temporary pylons above.
The Arch strut, connecting the two Arch ribs, is constructed at
segment 7. On top of the Arch ribs, at this location, precast column
segments for Pier 6 will be erected.
Attached to the top of the Arch ribs are temporary stairs, work
platforms, and cross rib access walkways. Workers climb these stairs
daily on their way to the form travelers.
High Resolution TIF (14 MB) |

looking east
View of the Nevada left from traveler, as seen from the right
traveler.
High Resolution TIF (14 MB) |

looking northwest
Looking up from the Nevada Arch rib towards the temporary pylons
above. Forestays span between the pylon heads and the Arch ribs,
sheathed in white HDPE casing. To the left of the left pylon, a set
of scaffolding stairs are attached to allow personnel access to the
pylon heads. These 155’ tall pylons will remain in place with the
stays attached to support the Arch until the Arch is completed.
After completion, all forestays, back stays, and pylons will be
removed.
High Resolution TIF (14 MB) |

looking north
View of the CO River Bridge (Mike
O'Callaghan-Pat Tillman Memorial Bridge) from downstream of the
Hoover Dam.
Left side of the picture
- The Arch, constructed to
segment 16 from the NV skewback. Forestay cables span from the Arch
ribs to the temporary pylons above Pier 5 and backstays span between
the temporary pylons and the backstay anchor block.
Right side of the picture
-
The Arch, constructed to segment 15, from the AZ skewback. Forestay
cables span from the Arch ribs to the temporary pylons above Pier 14
and backstays span between the head and the backstay anchor block.
High Resolution TIF (14 MB) |

looking north
Aerial view of the Mike O'Callaghan-Pat
Tillman Memorial Bridge looking to the north from above the Arizona
side of the canyon. The Arch is approximately 55% complete.
Left side of the picture
– The Nevada approach is visible with the Arch headings projecting
outward from the canyon wall. The Arch is constructed to segment
15. Forestay cables span from the Arch ribs to the temporary pylons
above Pier 5 and backstays span between the temporary pylon and the
backstay anchor block.
Right side of the picture
– The Arizona approach is visible with the Arch headings projecting
outward to segment 14. A set of backstay cables are attached to the
pylon heads, waiting tensioning as Arch construction progresses
outward.
High Resolution TIF (14 MB) |

looking south
Aerial view of the Mike O'Callaghan-Pat
Tillman Memorial Bridge looking to the south from above the Arizona
side of the canyon.
Left side of the picture
–
Backstay cables extend from the pylons to
the backstay anchor blocks. One set of backstays are attached to
the pylon head, waiting tensioning as Arch construction progresses
outward. A set of scaffolding stairs are attached to the South
pylon to allow personnel access to the pylon heads.
Right side of the picture
– The Arizona approach is visible with the left and right Arch ribs
constructed to segment 15. The form travelers are at segment 16
with the reinforcing cages installed. Five sets of forestay cables
extend from the temporary pylons above Pier 14 and attach to the
Arch ribs.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from February 2009 |
|
Colorado River Bridge...
|

looking south
View of the Obayashi / PSM, JV on-site concrete batch plant. From
this plant, all concrete for the project is currently being
produced.
High Resolution TIF (14 MB) |

looking southeast
View of the Arch from the existing US93 Nevada at the hairpin. A
concrete truck delivers another load of concrete to the awaiting
pump in Arizona
Foreground - From Nevada, the Arch, projects outward
from Pier 5 skewback footing. The vertical post tensioning bars
extend upwards from the Arch rib where Pier 6 will be erected, on
each side of the steel Arch strut that connects the two ribs. The
form travelers are at segment 13.
Background - The Arizona approach and Arch ribs are
visible across the canyon.
High Resolution TIF (14 MB) |

looking south
Obayashi / PSM, JV crews unload concrete into the re-mixer and
concrete pump located on the Arizona skewback footing at Pier 14.
Concrete is delivered to the pump by the cableway crane system via
an 8cy concrete bucket. From the pump, concrete is conveyed to the
placing boom where it is directed into the formwork of the Arch
segment under construction.
High Resolution TIF (14 MB) |

looking southeast
Inside the form traveler system at Arch Segment NV13-LT, Obayashi /
PSM, JV crews placed concrete into the bottom slab formwork. The
slick line from the end of the placing boom is directing the flow of
concrete through an open pour window in the formwork. Other crew
members consolidate the placed concrete while carpenters follow
behind and close the windows securely as placement advances.
High Resolution TIF (14 MB) |

looking south
Nevada Approach and Arch headings as viewed from the crest of Hoover
Dam during night time operations. The left and right ribs of the
Arch are constructed out to segment 13.
Four sets of forestay cables span from the Arch ribs to the
temporary pylons heads and the two sets of backstays span between
the head and the backstay anchor blocks. Additional forestays and
backstays are installed to the pylon heads, waiting tensioning as
Arch construction progresses outward.
High Resolution TIF (14 MB) |

looking south
Arizona Approach as viewed from the crest of Hoover Dam during night
time operations. The left and right ribs of the Arch are constructed
out to segment 12 with the form traveler advanced to segment 13
where construction crews place concrete for segment 13-LT. The
concrete placing boom reaches out from segment 11 and directs pumped
concrete into the formwork. Concrete is delivered by an 8cy bucket
from the bridge deck at Pier 14 to the awaiting concrete pump at the
skewback footing, where it is pumped up the North Arch rib in a pipe
to the placing boom.
Four sets of forestay cables span from the Arch ribs to the
temporary pylons heads and the two sets of backstays span between
the head and the backstay anchor blocks.
High Resolution TIF (14 MB) |

looking north
View of the Mike O'Callaghan-Pat Tillman Memorial Bridge as seen
from downstream of Hoover Dam. Presently the Arch is approximately
50% complete.
Left side of the picture - The Arch, constructed to
segment 13, from the NV skewback. Forestay cables span from the Arch
ribs to the temporary pylons above Pier 5 and backstays span between
the head and the backstay anchor block.
Right side of the picture - The Arch, constructed to
segment 12, from the AZ skewback. Forestay cables span from the Arch
ribs to the temporary pylons above Pier 14 and backstays span
between the head and the backstay anchor block.
High Resolution TIF (14 MB) |

looking north
On the Nevada Arch headings, Obayashi / PSM, JV crews launch the
inner core of the form traveler and position it in place for the
next segment to be constructed.
High Resolution TIF (14 MB) |

looking northwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from the deck of the bridge at Pier 14, looking towards
Nevada.
Top Left side of the picture – The left and right Arch
ribs project outward from the Nevada skewback, currently constructed
to segment 13.
Bottom of the picture – The left and right Arch ribs
in Arizona are visible, currently constructed to segment 13.
Temporary stay cables, sheathed in white HDPE casing, extend down to
the Arch from the temporary pylons above Pier 14.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from January 2009 |
|
Colorado River Bridge...
|

looking west
Crews from Steel Engineers complete the relocation of the
pre-assembled Arch Segment NV13-RT reinforcing steel cage from the
fabrication template on the Arizona approach to a staging bed. This
cage weighs approximately 25 tons.
High Resolution TIF (14 MB) |

looking northwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from the South side of Abutment 2 in
Arizona.
Right side of the picture – The completed Arizona
approach with the temporary pylons for the cable stays constructed
on top of Pier 14. The right and left Arch ribs are constructed to
segment 10 with the Arch strut installed at segment 7.
Center of the picture – The completed Nevada approach
with the temporary pylons for the cable stays erected on top of Pier
5. The right and left Arch ribs are constructed to segment 12 with
the Arch strut installed at segment 7.
Left side of the picture – Obayashi / PSM, JV survey
crew set up to survey across the canyon to a rod man on the North
Arch rib to make geometry control adjustments to the form traveler.
High Resolution TIF (14 MB) |

looking northwest
At the top of the South temporary pylon in Arizona, Obayashi / PSM,
JV crews utilize a winch system to pull into place backstay AO.
Visible at the right of this picture, forestays 3, 4, and 5 are
installed, connecting to and supporting the right Arch rib.
High Resolution TIF (14 MB) |

looking southeast
Looking down at the backstay anchor blocks, from the top of the
South temporary pylon in Arizona, Obayashi / PSM, JV crews fabricate
the next series of stay cables in the tray laying on the roadway
alignment.
At the top of the picture, the North and South backstay anchor
blocks are seen with stays DI and DO installed in each. Crews are
preparing for the installation of backstays AI and AO.
Visible near the top right of the picture, the inner core launching
rail of the right form traveler is being hoisted by the cableway
crane for placement on the form traveler at the leading edge of the
right Arch rib.
High Resolution TIF (14 MB) |

looking southeast
Looking down on the Arch from the roadway deck above Pier 5 in
Nevada, the right and left Arch ribs project outward over the
Colorado River below.
The left and right Arch ribs are constructed out to segment 12 with
reinforcing cages set for segments 12. Obayashi / PSM, JV carpenter
crews prepare to launch the inner core formwork of the form
travelers and install top slab formwork.
The Arch strut, connecting the two Arch ribs, is constructed at
segment 7. On top of the Arch ribs, at this location, precast column
segments for Pier 6 will be erected. A temporary bridge allows
worker’s access to the Arch from the existing US93 near the Nevada
hairpin area.
High Resolution TIF (14 MB) |

looking south
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from the crest of the Hoover Dam.
Piers 15 and 14 appear to the left in this picture, while Pier 5, 4,
3, 2, 1 appear to the right. Temporary pylons for the cable stays
are constructed on top of Piers 5 and 14 with forestay cables
spanning from the Arch ribs to the temporary pylons heads and
backstays spanning between the heads and the backstay anchor blocks.
The Arch is constructed to segment 10 in Arizona and to segment 12
in Nevada.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from December 2008 |
|
Colorado River Bridge...
|

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from the deck of the bridge at Pier 5, looking towards
Arizona.
The right and left Arch ribs are constructed out to segment 10. The
left rib has the reinforcing steel cage set for segment 11. Visible
at segment 7 is the steel strut member that connects both ribs
together. Temporary stay cables, sheathed in white PVC casing, are
attached to the arch ribs at segments 6, 8, and 10.
High Resolution TIF (14 MB) |

looking north
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from downstream of the Hoover Dam.
Left side of the picture - The Arch, constructed to
segment 10, from the NV skewback. Forestay cables span from the Arch
ribs to the temporary pylons above Pier 5 and backstays span between
the head and the backstay anchor block.
Right side of the picture - The Arch, constructed to
segment 10, from the AZ skewback. Forestay cables span from the Arch
ribs to the temporary pylons above Pier 5 and backstays span between
the head and the backstay anchor block.
High Resolution TIF (14 MB) |

looking southwest
Left side of the picture - The inner core of the
Arizona South form traveler system, weighing approximately 30 tons,
is removed from the Arch and carried by the South highline to the
Arizona approach for form resurfacing.
Right side of the picture – The two temporary pylons
above Pier 14 rise 155’ above the bridge deck. These towers are part
of the cable stay erection system that will support the arch ribs
until closure.
High Resolution TIF (14 MB) |

looking northwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) from the deck of the bridge at Pier 14, looking towards
Nevada.
Top Left side of the picture – The left and right Arch
ribs project outward from the Nevada skewback.
Center Left side of the picture – The inner core of
the Arizona South form traveler system is being hoisted by the
highline crane for resurfacing of the form panels.
Bottom of the picture – The left and right Arch ribs
in Arizona are visible with both inner core forms removed. Temporary
stay cables, sheathed in white PVC casing, extend down to the Arch
from the temporary pylons above Pier 14.
High Resolution TIF (14 MB) |

looking west
On the Arizona approach, Obayashi / PSM, JV carpenter crews
resurface the inner core of the form traveler.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from November 2008 |
|
Colorado River Bridge...
|

looking south
Inside the Nevada left Arch rib, an Obayashi / PSM, JV carpenter
constructs formwork for the diaphragm at Arch segment NV07-LT. The
portal through the wall of the Arch rib will allow access to the
strut.
High Resolution TIF (14 MB) |

looking east
Inside the Nevada left Arch rib, an Obayashi / PSM, JV carpenter
prepares to set formwork for the diaphragm at Arch segment NV07-LT.
Water will be pumped through the grey tubing after concrete
placement to cool the concrete during the curing period. The white
ducts encase the post tensioning bars that will extend upwards
through the exterior of the Arch rib, for the Pier 6 Left column.
High Resolution TIF (14 MB) |

looking south
Arizona Approach as viewed from the crest of Hoover Dam during night
time operations. The left and right ribs of the Arch are constructed
out to segment 9 with the form traveler advanced to and preparing
for construction of segment 10. The first and second sets of
forestay cables span from segments 6 and 8 to the temporary pylons
heads and the first set of backstays span between the head and the
backstay anchor block. Connecting the two ribs at segment 7 is a
temporary strut. This will remain in-place until the permanent strut
is erected.
High Resolution TIF (14 MB) |

looking east
As seen from the existing US93 Hairpin in Nevada, the left and right
Arch ribs project outwards over the Colorado River. The form
traveler systems are secured to segments NV10 and cantilevers out to
form segment NV11. Forestay cables span from the Arch ribs to the
temporary pylons above. The vertical post tensioning bars extend
upwards from the Arch rib where Pier 6 will be erected.
High Resolution TIF (14 MB) |

looking southwest
Nevada Approach and Arch headings as viewed from the crest of Hoover
Dam during night time operations. The left and right ribs of the
Arch are constructed out to segment 10. The first and second sets of
forestay cables span from the Arch ribs to the temporary pylons
heads and the first set of backstays span between the temporary
pylon head and the backstay anchor block.
High Resolution TIF (14 MB) |

looking northwest
View of an Arch strut as pre-assembled on the Arizona Approach. This
strut will be transported by the cableway cranes where it will be
erected between the Arch ribs at segment NV07.
High Resolution TIF (14 MB) |

looking northeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen during night time operations from downstream of
Hoover Dam.
Left side of the picture - The Arch, constructed to
segment 10, from the NV skewback. Forestay cables span from the Arch
ribs to the temporary pylons above Pier 5 and backstays span between
the head and the backstay anchor block.
Right side of the picture - The Arch, constructed to
segment 9, from the AZ skewback. Forestay cables span from the Arch
ribs to the temporary pylons above Pier 5 and backstays span between
the head and the backstay anchor block.
High Resolution TIF (14 MB) |

looking southwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) as seen from the roof of the Hoover Dam operations building.
Piers 15 and 14 appear to the left in this picture, while Pier 5 and
4 appear to the right. Temporary pylons for the cable stays are
constructed on top of Piers 5 and 14. The Arch projects outward from
the skewback footings at the base of Piers 5 and 14 while the twin
cableway cranes traverse the canyon above.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from October 2008 |
|
Colorado River Bridge...
|

looking southeast
Looking across the canyon from the bridge deck above Pier 5, the
left and right ribs of the Arizona Arch headings project outward
from Pier 14 skewback footing. Above the bridge deck, the temporary
pylons for the cable stays rise 155’. The pylon heads are accessed
by climbing the scaffolding stairway, attached to the right pylon.
High Resolution TIF (14 MB) |

looking south
Arizona Approach and Arch headings as viewed from the crest of
Hoover Dam. The left and right ribs of the Arch are constructed out
to segment 8 with the form traveler advanced to and preparing for
construction of segment 9. The first set of forestay cables span
from the Arch to the temporary pylons heads and the first set of
backstays span between the head and the backstay anchor block. The
North cableway crane is lowering materials to the awaiting crews at
the form travelers.
High Resolution TIF (14 MB) |

looking south
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from the crest of the Hoover Dam.
Piers 15 and 14 appear to the left in this picture, while Pier 5, 4,
3, 2, 1 appear to the right. Temporary pylons for the cable stays
are constructed on top of Piers 5 and 14. The Arch projects outward
from the skewback footings at the base of Piers 5 and 14.
High Resolution TIF (14 MB)
|

looking southwest
Nevada Approach and Arch headings as viewed from the crest of Hoover
Dam. The left and right ribs of the Arch are constructed out to
segment 9. The first and second sets of forestay cables span from
the Arch ribs to the temporary pylons heads and the first set of
backstays span between the head and the backstay anchor block.
High Resolution TIF (14 MB) |

looking northwest
Looking across the canyon from the bridge deck above Pier 14, the
left and right ribs of the Nevada Arch project outward from Pier 5
skewback footing. Above the deck, are the temporary pylons for the
cable stays with two sets of stays set in place for each Arch rib.
Beyond the pylons, the towers of the cableway cranes are luffted to
the North and South to position the loads they are hoisting above
their respective work areas. At the top left of this picture, chains
are visible, hanging down from the South cableway crane hook.
High Resolution TIF (14 MB) |

looking down
Looking down on the Arch from the roadway deck above Pier 5 in
Nevada, the right and left Arch ribs project outward over the
Colorado River below.
Left side of the picture – The left Arch rib is constructed
out to segment 9 and awaits the advancement of the form traveler. A
temporary bridge allows worker’s access to the Arch from the
existing US93 near the Nevada hairpin area.
Right side of the picture – The right Arch rib is constructed
to segment 8 and has the form traveler set for construction of
segment 9. Obayashi / PSM, JV carpenter crews prepare to install top
slab formwork.
High Resolution TIF (14 MB) |

looking southeast
Inside the Nevada left Arch rib, Steel Engineer’s iron workers place
reinforcing steel to construct the diaphragm at Arch segment
NV07-LT. Directly above this diaphragm, on the exterior of the Arch
rib, precast segments for Pier 6 Left will be erected.
Visible through the reinforcing steel, daylight shines in from the
leading face of the form traveler.
High Resolution TIF (14 MB)
|

looking west
As seen from the leading edge of the Nevada left from traveler, the
right traveler is set for construction of Arch segment NV10-RT.
Looking back down the Arch, the curvature takes shape.
The right column of Pier 5 projects from the Nevada skewback
footing. The fore cable stays, wrapped in white PVC sheathing, can
be seen extending from the Arch, to the temporary pylons above Pier
5.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from September 2008 |
|
Colorado River Bridge...
|

looking northwest
Left side of the picture – From the bridge deck of the
Arizona approach, a pre-assembled reinforcing cage for Arch segment
NV07-RT is hoisted by the South Cableway Crane and carried across
the canyon.
Right side of the picture – The temporary pylons for the
cable stays are constructed on top of Pier 14. The backstay cables
have been installed in the pylon head and await installation into
the backstay anchor block.
High Resolution TIF (14 MB) |

looking southeast
Crews from Steel Engineers prepare to set the pre-assembled
reinforcing cage for Arch segment NV07-RT into the form traveler
formwork.
High Resolution TIF (14 MB)
|

looking northeast
A carpenter foreman from the Obayashi / PSM, JV stands atop the
leading edge formwork of Arch segment NV08-LT, conversing with crews
working on the adjacent segment NV07-RT.
High Resolution TIF (14 MB) |

looking east
Obayashi / PSM, JV’s crews install embedments into the top slab
prior to completion of formwork for Arch segment NV07-RT.
High Resolution TIF (14 MB)
|

looking southeast
As seen from the Pier 5 skewback footing in Nevada, the left and
right Arch ribs extend outwards towards Arizona with work continuing
to cast segments NV07.
Across the canyon, columns of Pier 14 and the temporary pylons are
visible.
High Resolution TIF (14 MB) |

looking down
Looking down on the Arch from the roadway
deck above Pier 14 in Arizona, the right and left Arch ribs project
outward over the Colorado River below.
Left side of the picture
– The right Arch rib is constructed out to segment 6. Using the
Cableway Crane, iron workers place the pre-assembled reinforcing
cage for segment 7.
Right side of the picture
– The left Arch rib is constructed to segment 6 and has the form
traveler set for construction of segment 7.
High Resolution TIF (14 MB)
|

looking southeast
Obayashi / PSM, JV’s crews constructing formwork for Arch segment
NV07-LT.
Across the canyon, columns of Pier 14 temporary pylons, and the AZ
Arch are visible along with the Cableway Crane, lowering the
pre-assembled reinforcing cage for segment AZ-07 RT.
High Resolution TIF (14 MB) |

looking south
Lower right side of the picture – A pre-assembled reinforcing
cage for Arch segment AZ07-RT is hoisted by the South Cableway Crane
and carried across the canyon past the Arizona right form traveler.
Center of the picture – The temporary pylons for the cable
stays rise 155’ above the Arizona approach bridge deck at Pier 14.
Temporary cable stays are installed from the Arch to the pylon head
and will be used to support the Arch until the closure segment is
constructed. Near the bottom, the left and right Arch ribs project
outwards from the Pier 14 skewback footing, with the form travelers
set for Arch segments AZ07 left and right.
High Resolution TIF (14 MB)
|

looking northeast
Arizona Approach as viewed from down stream of Hoover Dam. The left
and right ribs of the Arch are constructed out to segment 6 with the
form traveler advanced to and preparing for construction of segment
7. The first set of forestay cables span from segment 6 to the
temporary pylons heads and the first set of backstays span between
the head and the backstay anchor block.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from August 2008 |
|
Colorado River Bridge...
|

looking south
View of the Arizona approach as seen from the crest of Hoover Dam.
The completed Arizona approach with the temporary pylons for the
cable stays constructed on top of Pier 14. At the base of Pier 14,
the left Arch rib is visible.
High Resolution TIF (14 MB)
|

looking southeast
View of the pre-assembled arch reinforcing steel cages stockpiled on
the Arizona approach.
High Resolution TIF (14 MB) |

looking down
Looking down on the Arch from the roadway deck above Pier 14 in
Arizona, the right and left Arch ribs project outward over the
Colorado River below.
Left side of the picture – The right Arch rib is constructed
out to segment 6 and awaits concrete placement.
Right side of the picture – The left Arch rib is constructed
to segment 6 and has the concrete placing boom extended to the right
Arch rib in preparation of concrete placement.
High Resolution TIF (14 MB)
|

looking north
Crews from Steel Engineers assembling arch reinforcing steel in a
template on the Arizona approach.
High Resolution TIF (14 MB) |

looking northwest
View of the temporary stay cable pylons constructed above Pier 14 in
Arizona. Crews are working on erecting the stairway scaffolding to
allow access to the pylon heads. Spanning overhead are the twin
cableway crane systems.
High Resolution TIF (14 MB)
|

looking north
View of the Arch struts as stockpiled on the Arizona Approach. Once
assembled, the strut will span between the Arch ribs to maintain
alignment.
High Resolution TIF (14 MB) |

looking south
As seen from the existing US93 Hairpin in Nevada, the left and right
Arch ribs project outwards over the Colorado River. The form
traveler systems are secured to segments NV06 and cantilevers out to
form segment NV07. the form traveler on the right rib of the Arch
has it’s left external form panel removed for maintenance.
High Resolution TIF (14 MB)
|

looking south
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from the crest of the Hoover Dam.
Piers 15 and 14 appear to the left in this picture, while Pier 5, 4,
3, 2, 1 appear to the right. Temporary pylons for the cable stays
are constructed on top of Piers 5 and 14. The Arch projects outward
from the skewback footings at the base of Piers 5 and 14.
High Resolution TIF (14 MB) |

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from the right of Abutment 1 in Nevada.
Left side of the picture – The completed Nevada approach with
the temporary pylons for the cable stays constructed on top of Pier
5. At the base of Pier 5, the right Arch rib is visible.
Right side of the picture – The completed Arizona approach
with the temporary pylons for the cable stays constructed on top of
Pier 14. At the base of Pier 14, the right and left Arch ribs are
visible.
Spanning the canyon overhead are the twin cableway cranes.
High Resolution TIF (14 MB)
|

looking west
View of the constructed stay cables as they lay on the Nevada
approach bridge deck, waiting insertion into the Arch and temporary
pylon head. These cables are part of the cable stay erection system
that will support the arch ribs until closure.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from July 2008 |
|
Colorado River Bridge...
|

looking west
Obayashi / PSM, JV’s temporary concrete batch plant, located in the
Boneyard laydown area.
High Resolution TIF (14 MB)
|

looking northwest
View of the south temporary stay cable anchor and highline crane at
the Abutment 1 area in Nevada. Utilizing steel beams, Obayashi / PSM
crews construct trays for fabrication of the stay cables between the
tower bases.
The south temporary stay cable anchor is exposed and is waiting
installation of the stays. The south highline crane system is
currently luffed to the north for delivery of materials to the Arch.
High Resolution TIF (14 MB) |

looking down
Looking down on the Arch from the roadway deck above Pier 5 in
Nevada, the right and left Arch ribs project outward over the
Colorado River below.
Left side of the picture – The left Arch rib is constructed
out to segment 6 and awaits the advancement of the form traveler. A
temporary bridge allows worker’s access to the Arch from the
existing US93 near the Nevada hairpin area.
Right side of the picture – The right Arch rib is constructed
to segment 6 and has the form traveler set for construction of
segment 7.
High Resolution TIF (14 MB)
|

looking southeast
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from the right of Abutment 1 in Nevada.
Left side of the picture – The completed Nevada approach with
the temporary pylons for the cable stays constructed on top of Pier
5. At the base of Pier 5, the right Arch rib is visible.
Right side of the picture – The completed Arizona approach
with the temporary pylons for the cable stays constructed on top of
Pier 14. At the base of Pier 14, the right and left Arch ribs are
visible.
Spanning the canyon overhead are the twin cableway cranes.
High Resolution TIF (14 MB) |

looking up
Utilizing the
cableway crane, Olsen Beal crews access
the top of the temporary stay pylons in Arizona to complete erection
of the pylon head assembly.
High Resolution TIF (14 MB)
|

looking south
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from the existing US93 in Nevada.
The completed Arizona approach is visible with the right and left
Arch ribs cantilevered outward from the Arizona Skewback at the base
of Pier 14.
High Resolution TIF (14 MB)
|

looking down
Looking down on the Arch from the roadway deck above Pier 14in
Arizona, the right and left Arch
ribs project outward over the Colorado River below.
Left side of the picture
– The right Arch rib is constructed out to segment 4 and awaits
final formwork and concrete placement for segment 5.
Right side of the picture –
The left Arch rib is constructed to segment 5 and awaits final
formwork and concrete placement for segment 6. Below segment 5, a
placing boom is attached to the Arch in preparation of concrete
placement.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from June 2008 |
|
Colorado River Bridge...
|

looking south
View of the Pier 5 columns as seen from the existing US93 Hairpin in
Nevada. Temporary scaffolding stairs allows access up the column to
survey control points. To the left of the base of the scaffolding,
the Arch form traveler system can be seen rising above the roadway
elevation.
High Resolution TIF (14 MB)
|

looking south
As seen from the existing US93 Hairpin in Nevada, the left and right
Arch ribs project outwards over the CO River. The fully configured
form traveler systems are secured to segment NV05 and cantilevers
out to form segment NV06.
High Resolution TIF (14 MB) |

looking southwest
Visible from the base of the Hoover Dam, the Arch begins to take
shape.
Left side of the picture – Arizona approach spans from
Abutment 2 to Pier 14. The Arch projects outward from the Pier 14
skewback footing. Temporary pylons for the cable stay erection
system are partially completed on the bridge deck above Pier 14.
Right side of the picture – The completed Nevada approach
span from Pier 4 to Pier 5, along with the left and right ribs of
the Arch are visible. Above Pier 5, the temporary pylons for the
cable stay erection system can be seen.
High Resolution TIF (14 MB)
|

looking southwest
View of the partially completed 155’ tall temporary pylon at Pier
14. These towers are part of the cable stay erection system that
will support the arch ribs until closure.
High Resolution TIF (14 MB)
|

looking west
The north highline crane system delivers the 6th precast segment to
waiting Olsen Beal workers at the top of the temporary pylon on the
right at Pier 14.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from May 2008 |
|
Interim Surfacing on the Arizona &
Nevada Approaches...
|

looking west
View of the completed Nevada approach portion of the project between
the Hoover Dam BOR Warehouse Bridge and the Hoover Dam Canyon
Bridge.
At the center of the picture, Las Vegas Paving personnel perform
clean up work near the Hoover Dam Lower Portal Road Bridge.
High Resolution TIF (14 MB)
|

looking east
View of the completed Nevada approach portion of the project between
the Hoover Dam Canyon Bridge and the Hoover Dam BOR Warehouse
Bridge.
High Resolution TIF (14 MB)
|

looking west
View of the completed Nevada approach portion of the project near
the Nevada interchange as seen from the existing US93.
A Las Vegas Paving water truck readies to wash the roadway alignment
in preparation for final project acceptance.
High Resolution TIF (14 MB)
|

looking west
View of the completed Nevada approach portion of the project as seen
from the existing US93.
At the bottom left of the picture, the Hoover Dam Canyon Bridge is
visible.
Near the top right of the picture, is the Nevada interchange, along
with the Goldstrike Canyon Road.
High Resolution TIF (14 MB)
|

looking southeast
View of the completed Arizona approach portion of the project as
seen from the Sugarloaf Mountain Bridge towards the Arizona
Interchange.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Colorado River Bridge...
|

looking northeast
Utilizing the highline crane system, Obayashi / PSM, JV workers
hoist and prepare to erect the first segment of the 155’ tall
temporary pylon at Piers 5 as part of the cable stay erection system
that will support the arch ribs until closure.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM, JV workers remove formwork and prepare to advance
the form traveler system from the recently constructed left arch rib
segment NV05 out to and reset for segment NV06.
Across the canyon, in Arizona, the left and right Arch ribs are
visible projecting from the skewback footing, nearly 1000’ away.
High Resolution TIF (14 MB)
|

looking south
View of the left and right Arch ribs as they project from the Pier 5
skewback footing in Nevada.
Foreground – The left rib is currently constructed out to
segment NV05.
Background – The right rib is currently constructed out to
segment NV04.
Workers access the form system by the temporary stairs attached to
the back of the arch ribs. As the Arch is constructed, additional
stairs will be added.
High Resolution TIF (14 MB)
|

looking west
View of the Nevada approach span of the Mike O'Callaghan-Pat Tillman
Memorial Bridge.
From left to right – The left and right ribs of the Arch
project from the Pier 5 skewback footing. Piers 5 through 1 are
completed along with the bridge deck spanning between them.
At the far right, the two towers of the twin highline crane system
can be seen.
High Resolution TIF (14 MB)
|

looking west
Obayashi / PSM, JV workers perform final checks of the Bidwell
concrete finishing machine prior to concrete placement for the deck
of Arizona approach from Pier 15 to Abutment 2.
Foreground – A side discharge conveyor system spans across
the deck to assist in concrete placement. The conveyor and the
finishing system travels towards Abutment 2 while placing the
freshly placed concrete.
High Resolution TIF (14 MB)
|

looking southwest
View of the Mike O'Callaghan-Pat Tillman Memorial Bridge alignment
looking from Arizona towards Nevada.
Left side of the picture – Arizona approach spans from
Abutment 2 to Pier 14. Olsen Beal crews install steel stay-in-place
decking between the girders prior to deck reinforcement placement.
Overhead, the highline crane system delivers materials to the work
area.
Right side of the picture – Across the canyon, the completed
Nevada approach span from Abutment 1 to Pier 5, along with the left
and right ribs of the Arch are visible.
High Resolution TIF (14 MB)
|

looking north
Preparing for concrete placement, Obayashi / PSM, JV workers
assemble the Bidwell concrete finishing machine on the Arizona
approach.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from April 2008 |
|
Interim Surfacing on the Arizona &
Nevada Approaches...
|

looking north
View of the completed pavement on the Arizona approach portion of
the project looking towards the Sugar Loaf Mountain Bridge.
High Resolution TIF (14 MB)
|

looking southwest
Las Vegas Paving placing the first lift of asphalt pavement on the
Nevada approach portion of the project.
High Resolution TIF (14 MB)
|

looking west
Arizona Highways Safety Systems driving posts for the guard rail in
Nevada.
High Resolution TIF (14 MB)
|

looking north
On the Arizona approach, Arizona Highways Safety Systems install
guard rail along the roadway alignment.
High Resolution TIF (14 MB)
|

looking south
Triple J Trenching constructing the slotted drain systems after the
paving is completed on the Arizona approach portion of the project.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Colorado River Bridge...
|

looking north
View of the bridge alignment looking towards Hoover Dam as seen from
downstream of the dam.
Left side of the picture:
Completed Nevada approach span from Abutment 1 to Pier 5. At the
bottom of Pier 5, the constructed Arch begins to project outward
over the CO River.
Right side of the picture:
the Arizona approach span from Abutment 2 to Pier 14 near
completion. At the bottom of Pier 14, the formwork for the Arch
segments are visible.
High Resolution TIF (14 MB)
|

looking northeast
Nevada approach from Abutment 1 to Pier 5.
At the center of the picture, Obayashi / PSM, JV workers prepare for
concrete placement for the bridge deck.
Near the top right, Olsen Beal crews install steel stay-in-place
decking prior to deck reinforcement placement.
High Resolution TIF (14 MB)
|

looking west
Obayashi / PSM, JV workers pre-assemble and attach access platforms
to precast temporary pylon towerheads.
High Resolution TIF (14 MB)
|

looking north
Ariel view of the Nevada approach from Abutment 1 to Pier 5. At the
bottom of Pier 5, the form traveler form system is cantilevered from
the completed Arch as it projects outward from the skewback.
High Resolution TIF (14 MB)
|

looking southeast
Ariel view of the Project alignment looking from Nevada towards
Arizona.
In the foreground, the Nevada approach span of the Mike
O'Callaghan-Pat Tillman Memorial Bridge is nearing completion.
Obayashi / PSM, JV workers prepare for the final concrete pour to
complete the bridge deck out to Pier 5.
In the background, the Arizona approach spans of the Mike
O'Callaghan-Pat Tillman Memorial Bridge are visible along with the
roadway alignment leading up to the bridge.
At the bottom center, the Pedestrian Plaza access ramp zigzags up
the mountainside from the future parking lot to allow access to the
bridge’s pedestrian walkway.
High Resolution TIF (14 MB)
|

looking south
View of the Arizona approach from Abutment 2 to Pier 14.
At the center of the picture, Olsen Beal crews install steel
stay-in-place decking between the girders prior to deck
reinforcement placement.
At the left, the two towers of the twin highline crane system can be
seen.
High Resolution TIF (14 MB)
|

looking north
Ariel view of the bridge alignment looking towards Hoover Dam.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from March 2008 |
|
Interim Surfacing on the Arizona &
Nevada Approaches...
|

looking south
Las Vegas Paving performing compaction of the asphalt pavement on
the Arizona approach portion of the project.
High Resolution TIF (14 MB)
|

looking south
Las Vegas Paving placing the first lift of asphalt pavement on the
Arizona approach portion of the project.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Colorado River Bridge...
|

looking northwest
In Arizona, pre-assembled Arch reinforcing steel cages are
stockpiled and await placement as part of an Arch segment.
High Resolution TIF (14 MB)
|

looking west
View of underside of bridge spans 1 and 2 as seen from the existing
US93 hairpin in Nevada.
Working approximately 95’ above the ground, an Obayashi / PSM, JV
worker attaches the temporary orange overhang falsework brackets to
the outside of the steel girder of span 2.
High Resolution TIF (14 MB)
|

looking east
View of spans 3 and 4 as seen from the deck of the bridge.
In the foreground, Obayashi / PSM, JV workers survey grade and
adjust the overhang falsework brackets on the outside of the steel
girder of span 2.
In the
background, Olsen Beal crews place stay
in-place decking for bridge span 3, between piers 3 and 4.
High Resolution TIF (14 MB)
|

looking southwest
Utilizing the south cableway crane system, Olsen Beal crews
transport and place steel stay in-place decking for bridge span 3,
between piers 3 and 4. Hanging on temporary supports between the
girders, the bridge deck drain piping system can be seen.
High Resolution TIF (14 MB)
|

looking southeast
View of the bridge alignment, looking from
Nevada towards Arizona.
In the foreground, crews from Steel
Engineers place reinforcing steel for the deck of span 1,
between Abutment 1 and Pier 1.
In the
background, Olsen Beal crews place stay
in-place decking for bridge span 3, between piers 3 and 4.
High Resolution TIF (14 MB)
|

looking southeast
View of the bridge alignment from the existing US93 hairpin in
Nevada looking towards Arizona.
In the foreground, Obayashi / PSM, JV workers place concrete for
Arch segment NV04-Left
In the background, across the Colorado River, the Arizona Arch
segments, along with Pier 14 columns are visible, approximately
1100’ away.
High Resolution TIF (14 MB)
|

looking south
As seen from the existing US93 hairpin in Nevada, during a night
shift operation, a concrete pump truck delivers concrete to Obayashi
/ PSM, JV workers for placement at Arch segment NV04-Left.
High Resolution TIF (14 MB)
|

looking northwest
View of a pre-assembled reinforcing steel cage being delivered to
Arch segment NV03-Right from the Abutment 2 area in Arizona. This
25’ long cage weighs approximately 32,000 pounds and is delivered
across the canyon with the south cableway crane system.
Visible just below the cage is the trolley assembly of the north
cableway crane system.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from February 2008 |
|
Interim Surfacing on the Arizona &
Nevada Approaches...
|

looking southeast
View of the Arizona approach roadway prior to aggregate base
placement. On ramp B, near the Arizona interchange, Triple J
Trenching is visible excavating and installing conduits for future
electrical crossings.
High Resolution TIF (14 MB)
|

looking west
Triple J Trenching crews place and compact backfill material for
installation of conduits for future electrical crossings on the
Arizona approach.
High Resolution TIF (14 MB)
|

looking northwest
On the Nevada approach, Las Vegas Paving is hauling, placing, and
compacting aggregate base material onto the Nevada approach roadway
alignment near the Nevada interchange.
High Resolution TIF (14 MB)
|

looking west
View of a haul truck placing aggregate base material onto the Nevada
approach roadway alignment near the Hoover Dam Canyon Bridge.
High Resolution TIF (14 MB)
|

looking south
Las Vegas Paving shaping aggregate base material prior to compacting
on the Nevada approach roadway alignment.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Colorado River Bridge...
|

looking east
The final span 2 steel girder is being transported from the abutment
1 area for placement in span 2. This girder is approximately 100’
long and weighs 45 tons.
High Resolution TIF (14 MB)
|

looking north
Olsen Beal crews prepare cable rigging for hoisting and erecting
steel girders for the Nevada approach.
High Resolution TIF (14 MB)
|

looking west
Delivery of the steel girders for the Nevada approach.
High Resolution TIF (14 MB)
|

looking east
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from abutment 1 in Nevada.
Steel girders for span 1 are erected with 3 of the 4 placed for span
2.
Olsen Beal crews are transported in a man basket to pier cap 3 in
preparation for erection of the final girder for span 2.
High Resolution TIF (14 MB)
|

looking northwest
View of the Nevada approach columns with steel girders in span 2
erected along with 2 of the 4 girders erected in span 3.
At the bottom of Pier 5, the completed Arch is visible cantilevered
off of the NV skewback footing.
High Resolution TIF (14 MB)
|

looking northwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from downstream of Hoover Dam.
At the left, the Nevada approach columns (Piers 1, 2, 3, 4, & 5) are
visible with steel girders in-place for spans 1, 2, and 3. Near the
bottom of Pier 5, newly constructed Arch segments cantilever off of
the NV skewback footing.
To the right, the Arizona approach columns (Piers 14 & 15) can bee
seen with the girder placement completed. Below Pier 14, on the AZ
skewback, formwork cantilevers off of the footing.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from January 2008 |
|
Colorado River Bridge...
|

looking southeast
Olsen Beal crews look on as the North highline crane hoists a 50 ton
concrete certification weight.
High Resolution TIF (14 MB)
|

looking southeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from abutment 1 in Nevada.
Center – The completed Pier 1 cap is awaiting steel
girder placement. System scaffolding encases the right column of
Pier 1.
Above the pier cap, the North highline crane is being certified
prior to use with a 50 ton concrete block test load.
High Resolution TIF (14 MB)
|

looking southeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from abutment 1 in Nevada. Both operational
highline cranes can be seen in their fully constructed
configuration.
Near the bottom of the photograph, piers caps for Piers 1, 2, 3, and
4 are visible.
High Resolution TIF (14 MB)
|

looking northwest
View of the CO River Bridge (Mike O'Callaghan-Pat Tillman Memorial
Bridge) progress as seen from downstream of Hoover Dam.
At the left, the Nevada approach columns (Piers 1, 2, 3, 4, & 5) are
visible awaiting steel girder placement.
To the right, the Arizona approach columns (Piers 14 & 15) can bee
seen with the girder placement nearing completion.
Spanning the canyon above the Approaches, the 3” track cables of the
highline cranes are visible.
High Resolution TIF (14 MB)
|

looking south
The 50 ton concrete block test load
traverses the canyon via the north highline crane.
At
the left of the photograph, the Arizona approach is visible.
High Resolution TIF (14 MB)
|

looking north
Crews from Steel Engineers assembling arch reinforcing steel in a
template on the Arizona approach.
High Resolution TIF (14 MB)
|

looking southwest
Obayashi / PSM, JV field engineer performs construction surveying
from the existing US93 near the Nevada hairpin area.
High Resolution TIF (14 MB)
|

looking northwest
View of the assembled precast temporary stay cable towerhead. These
towerheads will be constructed on top of a 130’ tall temporary tower
at Piers 5 and 14 as part of the cable stay erection system that
will support the arches until closure. At the completion of arch
construction, they will be removed along with the temporary stay
cables.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from December 2007 |
|
Colorado River Bridge...
|

looking southwest
View of the Nevada approach columns of the future CO River Bridge
(Mike O'Callaghan-Pat Tillman Memorial Bridge) as seen from the
existing US93 in Arizona.
From left to right:
In Arizona - Olsen Beal crews utilize a Manitowoc 2250
crane to assemble the trolley and attach the slack carriers for the
highline crane system
Piers 5, 4, 3, 2, 1 - columns are complete with their
pier cap visible above the cap falsework.
Abutment 1 – can be seen to the far right.
In Nevada - Olsen Beal crews utilize a Manitowoc M250
crane to perform work on the Nevada side of the highline crane
system.
High Resolution TIF (14 MB)
|

looking south
At the NV skewback footing, Obayashi / PSM, JV crews assemble the
form traveler to its full configuration onto the left Arch rib in
preparation for construction of the third segment.
To the right of this picture, an additional crew assembles formwork
in preparation for construction of right Arch rib segment two.
High Resolution TIF (14 MB)
|

looking southeast
High above the roadway alignment in Nevada, Olsen Beal crews
continue construction of the new highline crane systems.
High Resolution TIF (14 MB)
|

looking south
Utilizing a Manitowoc M250 crane located in the abutment 1 area in
Nevada; Olsen Beal crews attach the slack carriers onto the 3”
cables of the South highline crane system.
High Resolution TIF (14 MB)
|

looking northeast
In Arizona, steel girders make up a reinforcing steel fabrication
jig. On the exterior of this jig, iron workers will assemble Arch
segment reinforcing steel cages. Once complete, the cages will be
lifted off of the end of this jig and transported out to the form
traveler and placed as part of an Arch segment.
High Resolution TIF (14 MB)
|

looking southwest
In Arizona, high above the roadway alignment at Abutment 2, Olsen
Beal crews construct the highline crane system by attaching the
trolley and slack carriers to the 3” cables that span the canyon.
Below Pier 14, on the AZ skewback, formwork cantilevers off of the
footing in preparation for an arch segment concrete placement.
High Resolution TIF (14 MB)
|

looking northeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from downstream of Hoover Dam.
At the left, the Nevada approach columns (Piers 1, 2, 3, 4, & 5) are
visible awaiting steel girder placement. Near the bottom of Pier 5,
newly constructed Arch segments cantilever off of the NV skewback
footing.
To the right, the Arizona approach columns (Piers 14 & 15) can bee
seen with the girder placement completed.
The towers of the new highline crane system can bee seen to the edge
of the picture, along with their 3” cables spanning the canyon
between them.
High Resolution TIF (14 MB)
|

looking southwest
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from upstream of Hoover Dam.
Piers 15 and 14 appear to the left in this picture, while Pier 5, 4,
3, 2, 1 appear to the right.
Steel girders are in-place for the approach spans in Arizona while
crews construct the new highline crane system.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from November 2007 |
|
Colorado River Bridge...
|

looking north
In the contractor’s laydown yard, Obayashi / PSM, JV crews prepare
formwork to cast concrete panels for the exterior of the Arch strut
steel frames. A completed panel is hoisted by crane and transported
to the staging area, awaiting erection.
High Resolution TIF (14 MB)
|

looking west
In Nevada, Olsen Beal crews reeve cabling through an 18 part block
and tackle system for the backstay cable of the south highline crane
system.
High Resolution TIF (14 MB)
|

looking northwest
Nicholson Construction continue to drill through pipe sleeves and
nearly 60’ into solid rock to install post tensioning strand for the
Arizona left temporary backstay anchor block.
High Resolution TIF (14 MB)
|

looking west
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) alignment as seen from the existing US93 hairpin in
Nevada.
Piers 4, 3, 2, 1 - columns are complete with their
pier cap visible above the cap falsework.
Abutment 1 – can be seen to the far right. Beyond
Abutment 1, projects the towers of the twin highline crane systems.
Viewable high above the pier caps, the 3” diameter track cables for
the new highline system span the canyon between the Nevada and
Arizona highline towers.
High Resolution TIF (14 MB)
|

looking west
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from Arizona, looking towards Nevada.
In the foreground, steel girders span between Abutment 2 to Pier 15,
then from Pier 15 to Pier 14.
Across the canyon, the two white towers of the twin highline crane
systems can be seen in Nevada.
High Resolution TIF (14 MB)
|

looking south
View of half of the lower support structure of the form traveler
system as it is being prepared for installation onto the left Arch
rib in Nevada. This support structure forms the bottom of the Arch
segment while concrete is placed.
High Resolution TIF (14 MB)
|

looking west
In Nevada, Olsen Beal crews reeve cabling through an 18 part block
and tackle system for the backstay cable of the south highline crane
system.
High Resolution TIF (14 MB)
|

looking west
Utilizing a Manitowoc 2250 crane located in the abutment 2 area in
Arizona; Olsen Beal crews continue assembling the new highline crane
system.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from September & October 2007 |
|
Colorado River Bridge...
|

looking west
Utilizing a Manitowoc 2250 crane located in the abutment 2 area in
Arizona; Olsen Beal crews disassemble and prepare the S-70 Derrick
Crane for removal and demobilization.
High Resolution TIF (14 MB)
|

looking south
View of the new slack carriers awaiting installation on the highline
crane system.
High Resolution TIF (14 MB)
|

looking west
View of the completed Nevada towers for the new highline crane
system located at the abutment 1 area in Nevada. These towers are
335’ tall.
High Resolution TIF (14 MB)
|

looking northeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from Arizona, looking towards Nevada.
At the right of the picture, red temporary bracing project out from
span 15 to form the deck overhang.
Across the canyon, a Manitowoc 2250 crane located at the Nevada
hairpin on existing US93 delivers materials and workers to the top
of Pier 5. Visible beyond it are the columns of the Nevada approach
and new highline crane towers.
High Resolution TIF (14 MB)
|

looking south
View of the Nevada approach columns as
seen from the crest of Hoover Dam.
From left to right:
Pier 5
– At the top, Obayashi / PSM, JV personnel
stress the pier cap transverse post tensioning.
At the bottom, formwork projects
outward from the skewback footing, forming the first two segments of
the Arch.
Piers 4, 3,
2, 1 - columns are complete with their pier cap visible
above the cap falsework.
Abutment 1
– can be seen to the far right. Beyond Abutment 1, projects the
tops of the twin highline crane systems.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from August 2007 |
|
Colorado River Bridge...
|

looking west
View of the erected steel girders for spans 15 and 16 as seen from
Abutment 2 in Arizona. The bridge deck elevation will be
approximately 9” above the girders top flange. In the background,
Olsen Beal erects the Nevada towers for the new highline crane
system.
High Resolution TIF (14 MB)
|

looking west
Obayashi / PSM, JV crews continue to construct overhang brackets and
formwork onto the edge of the span 16 girder.
Across the canyon, in the abutment 1 area in Nevada, Olsen Beal
crews erect the Nevada towers for the new highline crane system. To
the right of this picture, the Manitowoc 2250 crane located at the
Nevada hairpin on existing US93 is stored in it’s laid down, non-use
configuration.
High Resolution TIF (14 MB)
|

looking west
View of the Nevada approach columns of the future CO River Bridge
(Mike O'Callaghan-Pat Tillman Memorial Bridge) as seen from the
existing US93 in Arizona.
From left to right:
Pier 5 – System scaffolding encases the right column
for concrete finishing operations. At the bottom of Pier 5, formwork
projects outward from the skewback footing, forming the first two
segments of the Arch.
Piers 4, 3, 2, 1 - columns are complete with their
pier cap visible above the cap falsework.
Abutment 1 – can be seen to the far right.
High Resolution TIF (14 MB)
|

looking south
Utilizing a Manitowoc M250 crane located in the abutment 1 area in
Nevada; Olsen Beal crews erect the Nevada towers for the new
highline crane system. The one on the left is currently 240’ while
the one on the right is 160’ tall. When completed these towers will
top out at 335’ in height.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM, JV utilizing the S-70 Derrick Crane at Abutment 2 in
Arizona to remove the temporary bracing between piers 14 and 15
through an opening in the steel girder alignment. Once complete, the
final girder of span 15 will be set.
At the bottom left of this picture, crews continue to form the
foundation blocks of the Arizona towers for the new highline crane
system.
High Resolution TIF (14 MB)
|

looking west
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from Arizona, looking towards Nevada.
In the foreground, at the abutment 2 area, work continues on
construction of the foundation blocks of the Arizona towers for the
new highline crane system, along with the completion of girder
erection for spans 15 and 16.
Across the canyon, a Manitowoc 2250 crane located at the Nevada
hairpin on existing US93 delivers materials and workers to the top
of Pier 5. Visible beyond it are the columns of the Nevada approach.
High Resolution TIF (14 MB)
|

looking northeast
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from downstream of Hoover Dam.
At the left, the Nevada approach columns (Piers 1, 2, 3, 4, & 5) are
visible awaiting steel girder placement.
To the right, the Arizona approach columns (Piers 14 & 15) can bee
seen with the girder placement nearing completion.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from July 2007 |
|
Colorado River Bridge...
|

looking east
View of new stockpiled Cableway Crane cables located on the Nevada
approach awaiting erection.
High Resolution TIF (14 MB)
|

looking south
Nicholson Construction utilizing a Manitowoc M250 crane to transport
drilling equipment and materials to the location of the luffing guy
anchor block for the new Cableway Crane system near the Abutment 1
area.
High Resolution TIF (14 MB)
|

looking south
Utilizing the Manitowoc 2250 crane located at the Nevada hairpin on
existing US93, Olsen Beal crews construct falsework for the Pier 5
cap. Workers walk the steel beams situated 860’ above the Colorado
River.
System scaffolding encases the columns of Pier 5 to allow access for
grouting and concrete finishing operations.
To the right of Pier 5, Pier 4 can be seen.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM, JV utilizing the S-70 Derrick Crane and a yellow man
basket at Abutment 2 in Arizona to access the Pier 14 skewback
footing where crews continue to form Arch segments.
Above the man basket, the formwork for Pier 14 pier cap can be seen.
Concrete placement for this cap took place during the night time
hours on July 20, 2007.
To the left of Pier 14, completed Pier 15 along with its cap can be
seen.
High Resolution TIF (14 MB)
|

looking northwest
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from Arizona, looking towards Nevada.
Across the canyon, a Manitowoc 2250 crane delivers materials and
workers to the top of Pier 5. At the bottom of Pier 5, formwork
projects outward from the skewback footing, forming the first two
segments of the Arch. The blue formwork is the inner core of the
Arch form traveler system. This system will be utilized to form the
hollow inner portion of the Arch.
High Resolution TIF (14 MB)
|

looking southwest
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) as seen from the existing US93 hairpin in Nevada.
From left to right:
Pier 5 – system scaffolding encases the columns for
grouting and concrete finishing operations. At the pier cap,
carpenters continue to set falsework.
Piers 4, 3, 2, 1 - columns are complete with their
pier cap visible above the cap falsework.
Abutment 1 – can be seen to the far right.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from June 2007 |
|
Colorado River Bridge...
|

looking west
Olsen Beal crews erecting precast segments for Pier 14 left column.
Visible to the right and left are the completed columns of Pier 15.
High Resolution TIF (14 MB)
|

looking west
View of the formwork for the Pier 15 cap, ready for concrete
placement.
In the background, visible between Pier 15 columns, Olsen Beal crews
continue erecting precast segments for Pier 14 left.
High Resolution TIF (14 MB)
|

looking south
View of Piers 14 and 15 as seen from the crest of the Hoover Dam.
Olsen Beal crews utilizing the S-70 Derrick crane at Abutment 2 in
Arizona to transport precast segments and erect Pier 14 left column.
To the left of Pier 14, the completed columns of Pier 15 along with
the formwork for the cap can be seen.
High Resolution TIF (14 MB)
|

looking south
Olsen Beal utilizing the Manitowoc 2250 crane located at the Nevada
hairpin on existing US93 to erect precast segments for Pier 5 left
column.
High Resolution TIF (14 MB)
|

looking southwest
View of precast column segments, delivered to the Abutment 2 area,
in preparation for transport to their respective columns by the S-70
Derrick crane.
High Resolution TIF (14 MB)
|

looking south
View of the bridge alignment as seen from the crest of the Hoover
Dam.
Piers 15 and 14 appear to the left in this picture, while Pier 5, 4,
3, 2, 1 appear to the right.
High Resolution TIF (14 MB)
|

looking southwest
View of the delivered steel box girders, staged at the Abutment 2
area.
High Resolution TIF (14 MB)
|

looking north
Obayashi / PSM, JV continuing to assemble the inner core form of the
Arch form traveler system. This system will be utilized to form the
hollow inner portion of the Arch.
High Resolution TIF (14 MB)
|

looking north
Subcontractor, Nicholson, drilling holes for the rock anchors of the
new highline back stay anchor located in Arizona near abutment 2.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from May 2007 |
|
Colorado River Bridge...
|

looking east
Olsen Beal utilizing the S-70 Derrick crane at Abutment 2 in Arizona
to transport precast segments and erect Pier 14 right column.
Visible above Pier 14 is the completed columns of Pier 15.
High Resolution TIF (14 MB)
|

looking south
Olsen Beal utilizing the Manitowoc 2250 crane located at the Nevada
hairpin on existing US93 to erect precast segments for Pier 5 right
column.
Visible to the right of Pier 5 is the completed columns of Pier 4.
High Resolution TIF (14 MB)
|

looking west
View of the South temporary stay cable anchor block located in
Arizona near Abutment 2.
High Resolution TIF (14 MB)
|

looking southeast
View of the bridge alignment at abutment 1.
From left to the right –
Completed Pier 2 can be seen with the formwork removed from its pier
cap. Pier 1 has the falsework in place waiting for reinforcing steel
/ formwork to construct the pier cap. The temporary stay cable
anchor blocks are visible in the roadway alignment to the right of
the abutment. Near the yellow Grove crane, the old Highline Crane
tower foundations are being prepared for removal by blasting.
To the left of the temporary stay cable anchor blocks, the
Pedestrian Access ramp zigzags up the mountainside from the future
access parking lot where the construction office trailers are
currently located.
High Resolution TIF (14 MB)
|

looking northeast
View of the bridge alignment looking towards Hoover Dam.
Left side of the picture –
Completed Pier 2, 3, and 4. Pier 5 right / left columns are in
various stages of erection. Falsework for the Arch cantilevered off
of the Pier 5 skewback footing.
Right side of the picture –
Falsework for the Arch cantilevered off of the Pier 14 skewback
footing. Pier 14 right / left columns are in various stages of
erection. The S-70 Derrick crane is setting precast segments for the
Pier 15 left column from Abutment 2. Pier 15 right column is
competed.
High Resolution TIF (14 MB)
|

looking northwest
View of the bridge alignment looking from Abutment 2 (Arizona)
towards Abutment 1 (Nevada).
Foreground: completed Pier 15 columns are wrapped in
scaffolding.
Background: Falsework for the Arch is cantilevered off of the
Pier 5 skewback footing. Above the falsework, Pier 5 can be seen
with crew erecting segments for the right column. Pier 4 is visible
with the pier cap falsework in place.
High Resolution TIF (14 MB)
|

looking northwest
Looking down at Pier 5 skewback footing on completed Arch segments
NV01 Right and Left. The falsework for segments 2 projects out over
the canyon, ready for formwork / reinforcing steel placement.
High Resolution TIF (14 MB)
|

looking northwest
View of the bridge alignment looking from Abutment 2 (Arizona)
towards Abutment 1 (Nevada) from above Abutment 2.
Foreground: Excavations for the temporary stay cable anchor blocks
are visible in the roadway alignment near the footing of the S-70
Derrick crane. The crane is currently setting precast segments for
the erection of Pier 15 left column.
Background: Pier 5 and the Arch segments in various stages of
construction. Next are the completed Pier 4, 3, 2. Pier 1 that can
be seen with the falsework in place for the pier cap construction.
Abutment 1 is visible behind Pier 1.
High Resolution TIF (14 MB)
|

looking northwest
Looking down on Olsen Beal crews preparing to set the next precast
segment at Pier 5 right as they work 230 feet above the skewback
footing.
Visible below are the completed Arch segments NV01 Right and Left
along with the falsework for segments 2.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from April 2007 |
|
Colorado River Bridge...
|

looking east
Olsen Beal utilizing the S-70 Derrick Crane at Abutment 2 in Arizona
to transport precast segments and erect Pier 15 right and left
columns.
Visible below Pier 15 is the skewback footing of Pier 14 with the
falsework for the Arch protruding outward.
High Resolution TIF (14 MB)
|

looking west
View of the South temporary stay cable anchor block located in
Nevada near Abutment 1.
High Resolution TIF (14 MB)
|

looking west
View of delivered concrete being cooled with liquid Nitrogen prior
to placement for construction of the Arch segment NV01-RT.
High Resolution TIF (14 MB)
|

looking southwest
View of the future CO River Bridge (Mike O'Callaghan-Pat Tillman
Memorial Bridge) alignment as seen from the existing US93 hairpin in
Nevada.
Abutment 1 in final stages of construction with the blockouts for
the tie back anchors remaining to be filled.
Pier 1 is shown with falsework for the pier cap in
place.
Pier 2 can be seen with the completed pier cap.
Pier 3 is visible with the completed pier cap along
with climbing scaffolding surrounding the columns.
Pier 4 is visible with the completed pier cap.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from March 2007 |
|
Colorado River Bridge...
|

looking west
Workers from Jake’s Crane prepare for the removal of the counter
weights from the
Link Belt TG1900
erected on the Pier 15 left foundation. This worker is attaching
hoisting slings onto the weights wile perched nearly 865’ above the
Colorado River.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM,
JV utilizing a Manitowoc 2250 crane to construct / access Piers 3
and 4 from the Nevada
hairpin on existing US93.
High Resolution TIF (14 MB)
|

looking west
View of the bridge alignment as seen from
Arizona towards Nevada.
Piers 1, 2, 3,
4, 5 in various stages of completion. Formwork for Arch segments
NV01N and NV01S can be seen cantilevered off of the Pier 5 (NV
skewback) footing.
High Resolution TIF (14 MB)
|

looking southwest
Jake’s Crane utilizing the S-70 Derrick
Crane at Abutment 2 in Arizona to dismantle the Link Belt
TG1900 from the Pier 15 left foundation.
Visible to the
left of the crane is Pier 15 right in partial stage of completion.
High Resolution TIF (14 MB)
|

looking north
Crane close-up.
High Resolution TIF (14 MB)
|

looking north
Workers from Jake’s Crane utilizing the S-70 Derrick Crane at
Abutment 2 in Arizona to dismantle the
Link Belt TG1900
from the Pier 15 left foundation. Crews are removing the boom
section and transporting it to the laydown area on the Arizona
approach roadway.
High Resolution TIF (14 MB)
|

looking east
View of the future CO River Bridge (Mike
O'Callaghan-Pat Tillman Memorial Bridge)
alignment as seen from Nevada, looking towards Arizona.
Abutment 1 in final stages of construction with the
blockouts for the tie back anchors remaining to be filled.
Pier 1 is shown with falsework for the pier cap in
place.
Pier 2 can be seen with formwork for the pier cap in
place. Concrete placement for the cap was performed on August 21,
2006.
Pier 3 is visible with formwork for the pier cap in
place. Concrete placement for the cap was performed on March 27th.
Pier 4
is visible with formwork for the pier cap in place. Ironworkers are
placing reinforcing steel for the cap.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from February 2007 |
|
Colorado River Bridge...
|

looking northwest
Dielco Crane assembles and attaches the luffing jib to the Manitowoc
2250 crane at the existing US93 near the hairpin in Nevada.
High Resolution TIF (14 MB)
|

looking northDielco Crane assembling a
Manitowoc 2250 crane to be utilized at the existing US93 near the
hairpin in Nevada.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM, JV personnel constructing falsework for the Pier 4
pier cap in the work access area of the existing US93 near the
hairpin in Nevada.
High Resolution TIF (14 MB)
|

Overall View #1.
High Resolution TIF (14 MB)
|

Overall View #2
.
High Resolution TIF (14 MB)
|

looking west
Obayashi / PSM, JV and Olsen Beal personnel
assembling the 70 foot mast for the S-70 Derrick Crane near Abutment
2 in Arizona.
High Resolution TIF (14 MB)
|

looking southwest
Obayashi / PSM, JV and Olsen Beal prepare to raise and install the 70 foot
mast for the S-70 Derrick Crane near Abutment 2 in Arizona.
High Resolution TIF (14 MB)
|

looking east
View of the future CO River Bridge (Mike
O'Callaghan-Pat Tillman Memorial Bridge) alignment as seen from
Nevada, looking towards Arizona. Visible to the lower left of this
photograph is the nearly completed pedestrian access ramp as it
zigzags up the mountain side onto the alignment near Abutment 1.
High Resolution TIF (14 MB)
|

looking north
View of the bridge alignment as seen from downstream of the Hoover
Dam.
Left Center: Piers 1, 2, 3, 4, 5 in various stages of
completion. Formwork for Arch segments NV01N and NV01S can be seen
cantilevered off of the Pier 5 (NV skewback) footing.
Right Center: Pier 14 (AZ skewback) footing, Pier 15, and
abutment 2 are visible. The Link Belt TG1900 Tower Crane remains
erected on the left footing foundation of Pier 15.
High Resolution TIF (14 MB)
|

looking northeast
Ladd &
Associates place back fill material at Abutment 1 in Nevada.
High Resolution TIF (14 MB)
|

looking south
Obayashi / PSM, JV utilizing a Manitowoc 2250 crane to construct /
access Piers 3 and 4 from the Nevada hairpin on existing US93.
High Resolution TIF (14 MB)
|

looking south
Subcontractor, Nicholson, drilling holes for the
rock anchors on the north temporary backstay anchor block in Nevada
near abutment 1.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from January 2007 |
|
Colorado River Bridge...
|

looking west
Obayashi / PSM, JV personnel stockpiling system scaffolding
materials in the work access area of the existing US93 near the
hairpin in Nevada.
High Resolution TIF (14 MB)
|

looking east
View of the S-70 Derrick Crane bracing to be
erected near Abutment 2 in Arizona. This crane will be utilized to
erect Piers 14 and 15 and construct portions of the Arch from the
Arizona side of the canyon.
High Resolution TIF (14 MB)
|

Obayashi / PSM, JV crews place concrete to construct the south Back
Stay Anchor block near Abutment 1 in Nevada.
High Resolution TIF (14 MB)
|

looking west
Obayashi / PSM, JV utilizing a Grove GMK6350 truck
crane to remove system scaffolding from Pier 2 left.
From left to right appear Pier 4 left with system scaffolding
erected around its column, Pier 3 has climbing scaffolding
attached to allow access for grouting / finishing operations,
Pier 2 is currently having the system scaffolding removed.
Behind Pier 2, Pier 1 and Abutment 1 can be seen.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from November/December 2006 |
|
Colorado River Bridge...
|

looking west
View of the bridge alignment looking from Abutment 2 (Arizona)
towards Abutment 1 (Nevada).
Foreground: Reinforcing steel for the Abutment 2
backwall protrudes upwards. Further out, Pier 15 Right in the
current erection stage while the Link Belt TG1900 tower crane
remains erected on Pier 15 Left footing.
Background: Pier 5 is in the erection stage. Behind
Pier 5, Pier 4 is visible with the pier cap falsework in
place.
High Resolution TIF (14 MB)
|

looking north
View of Nevada Approach piers as seen from the
Colorado River elevation just downstream of the Hoover Dam. Visible
from the left to the right are Piers 1 through 5. The formwork for
the arch starter segments is cantilevered off of the Pier 5 skewback
footing, protruding out over the canyon wall. Temporary bracing
spans between Piers 2 to Pier 4. Once Pier 5 is erected to the
temporary bracing elevation, additional sections will be set to
connect to Pier 4.
High Resolution TIF (14 MB)
|

looking north
Obayashi / PSM, JV and Cross Marine Projects utilizing a crane and
dive team to remove fallen Cableway Crane System debris from the
Colorado River. Crews were staged at the river’s edge on top of the
Hoover Dams’ Nevada spillway tunnel structure.
High Resolution TIF (14 MB)
|

looking southeast
View of Arizona Approach as seen from the existing
US93 near the hairpin in Nevada.
High Resolution TIF (14 MB)
|

looking southwest
Obayashi / PSM, JV utilizing a Grove GMK6350 truck crane to access
Piers 3 through 5 from the existing US93 at the hairpin turn in
Nevada. From left to right appear Pier 4 with its pier cap
falsework partially constructed, Pier 3 has climbing
scaffolding attached to allow access for grouting / finishing
operations, and Pier 2 has system scaffolding erected around
its columns to allow access to the pier cap. Behind Pier 2, Pier
1 and Abutment 1 can be seen.
High Resolution TIF (14 MB)
|

looking southwest
View of Hoover Dam and Nevada Approach as seen from
the Hoover Dam visitor parking area in Arizona.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from October 2006 |
|
Colorado River Bridge...
|

looking southeast
Obayashi / PSM, JV personnel loading the last segments of the
collapsed South Cableway Crane towers at
the Abutment 1 area in Nevada.
High Resolution TIF (14 MB)
|

Obayashi / PSM, JV personnel are utilizing a crane to access Pier 4
to remove a temporary protection beam from the side of the columns.
To the right of Pier 4, visible is Pier 3 with access scaffolding
projecting up from the ground.
Behind Pier 3, Pier 2 can be seen with its completed pier cap in
place.
High Resolution TIF (14 MB)
|

looking east
View of Abutment 1 with backfilling
operation nearing completion.
High Resolution TIF (14 MB)
|

looking west
Ladd & Associates utilizing hoppers to transport backfill material
for the backfilling of Abutment 2.
High Resolution TIF (14 MB)
|

looking west
View of the approach spans looking from Pier 5 to Abutment 1 as seen
from the Nevada hairpin on existing US93.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from September 2006 |
|
Colorado River Bridge...
|

View of the collapsed North and South Cableway Crane system looking
from Nevada towards Arizona.
High Resolution TIF (14 MB)
|

View of the collapsed North and South Cableway Crane system at
Abutment 2 area in Arizona.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from August 2006 |
|
Colorado River Bridge...
|

View of the Colorado River Bridge alignment looking East from Nevada
towards Arizona.
Pictured from left to right:
Abutment 1 in final stages of construction.
Pier 1 is shown with falsework for the pier cap in
place.
Pier 2 is shown with pier cap formwork in place ready
for concrete placement.
Pier 3 is shown with falsework for the pier cap in
place.
Pier 4 is in the erection stage awaiting falsework for
the pier cap.
Pier 5 right is in the erection stage
High Resolution TIF (14 MB) |

View of the bridge alignment looking East from Nevada towards the
Arizona side of the canyon.
From the bottom to the top:
Pier 14 Skewback footing is complete. On the temporary
work platform, Nicholson Construction is drilling for the temporary
tie back anchors through the footing into the canyon wall.
A Link Belt TG1900 tower crane is erected on Pier 15
left footing. Pier 15 right is in its initial stages
of erection with several segments placed.
The formwork for Abutment 2 appears near the center of
this picture.
High Resolution TIF (14 MB) |

The bridge alignment looking West from Arizona towards the Nevada
approach spans. Pictured from bottom to top.
Visible is the formwork for the Arch starter segments attached to
the Pier 5 Skewback footing. Above the footing, crews
on Pier 5 continue to erect precast segments. All of
the precast segments for Piers 1 through 4 have been erected and the
pier caps are in various stages of construction. Grey colored
temporary bracing can been seen attached between Pier 4
and Pier 3 and between Pier 3 and
Pier 2. Overhead, the cableway cranes provide personnel
access and material deliveries to the pier columns.
High Resolution TIF (14 MB) |

Looking East
Ladd & Associates in the process of backfilling the Abutment 1.
Projecting on an angle through the right retaining wall and the
abutment are the tie back anchors. Visible through Abutment 1
backwall reinforcing steel is the falsework for the Pier 1 pier cap
and the formwork for the Pier 2 pier cap.
High Resolution TIF (14 MB) |

Looking SouthwestView of the Abutment 2 stem wall
in preparation for concrete placement after formwork and reinforcing
steel have been constructed.
High Resolution TIF (14 MB) |

Looking West
View of the approach spans looking from Pier 4 to Abutment 1 as seen
from the Nevada hairpin on existing US93.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from July 2006 |
|
Colorado River Bridge...
|

(looking east)View of the Colorado River
Bridge alignment looking from Nevada towards Arizona. Pictured from
left to right:
Abutment 1 in final stages of construction. Formwork for
panels 1 and 3 of the nearly 57’ tall retaining wall being placed.
Pier 1 is shown with falsework for the pier cap in place.
Pier 2 is shown with falsework for the pier cap in place.
Pier 3 is in the erection stage.
Pier 4 is in the erection stage awaiting temporary wind
bracing placement.
High Resolution TIF (14 MB)
|

(looking south)Obayashi / PSM, JV
personnel placing concrete for the Pier 14 footing (Arizona
skewback). Nearly 2200 cubic yards of concrete was placed, all of
which was pumped though the twin 700’ long pipes (slick line)
extending from the Abutment 2 area into Pier 14 which can be seen
bolted to the excavation wall.
Reinforcing steel for the South arch is visible extending out of the
face of the formwork.
High Resolution TIF (14 MB)
|

(looking east)Obayashi / PSM, JV personnel
placing concrete for the Pier 14 footing (Arizona skewback). Two 32
meter concrete placing booms were utilized to accurately distribute
the concrete into the formwork.
Reinforcing steel for the North arch is visible extending out of the
face of the formwork.
High Resolution TIF (14 MB)
|

(looking south)Obayashi / PSM, JV
personnel working late into the night placing concrete for the Pier
14 footing (Arizona skewback).
High Resolution TIF (14 MB)
|

(looking southwest)View of the Nevada
approach columns looking from Pier 4 to Abutment 1.
High Resolution TIF (14 MB)
|

(looking east)At the Liquid Nitrogen (LN2)
cooling station, Liquid Nitrogen is being injected into concrete
mixer trucks to cool the freshly batched concrete.
High Resolution TIF (14 MB)
|

(looking southwest)Olsen Beal utilizing
the two cableway cranes in tandem to erect the temporary bracing
between Pier 2 and 3.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from June 2006 |
|
Colorado River Bridge...
|

(looking east)View of the Colorado River
Bridge alignment looking from Nevada towards Arizona. Pictured from
left to right:
Abutment 1 in final stages of
construction. Formwork for the second lift on the retaining wall
being placed.
Pier 1 is shown with falsework for the
pier cap in place.
Pier 2 is erected to pier cap elevation.
Pier 3 is in the erection stage awaiting
temporary wind bracing placement.
Pier 4 right, Olsen Beal crews utilizing
the cableway crane to set a precast segment.
High Resolution TIF (14 MB)
|

(looking southeast)View of the bridge
alignment looking towards the Arizona side of the canyon. From the
bottom to the top:
Pier 14 Skewback footing formwork is completed awaiting
concrete placement. As seen to the right of the excavation, twin
700’ long pipes (slick line) extend from the Abutment 2 area into
Pier 14 for placement of concrete by pumping.
A Link Belt TG1900 tower crane is erected on Pier 15 left
footing.
The formwork for Abutment 2 appears near the center of this
picture.
High Resolution TIF (14 MB)
|

(looking southeast)
Precast column
segments staged near abutment 1 awaiting placement for the approach
span columns.
High Resolution TIF (14 MB)
|

(looking southwest)Left: Olsen Beal
personnel utilizing the cableway crane to set another segment for
the Pier 4 right column.
Center: Crews from Jake’s Crane dismantling the Link Belt
TG1900 tower crane erected on Pier 4 left footing.
Right: Temporary scaffolding is attached to the sides of Pier
3 left column to provide access during final stages of erection.
This scaffolding is utilized during segment erection and subsequent
post tensioning bar grouting operations.
High Resolution TIF (14 MB)
|

View of the approach spans looking from
Pier 3 to Abutment 1.
High Resolution TIF (14 MB)
|

(looking northwest)View of the approach
spans looking from Pier 3 to Abutment 1.
High Resolution TIF (14 MB)
|

(looking south)Close up view of Olsen Beal
personnel setting a precast segment for the Pier 4 right column.
High Resolution TIF (14 MB)
|

(looking northwest)The bridge alignment
looking from Arizona straight towards the Nevada approach spans.
Pictured from bottom to top.
Nicholson Construction drilling for the temporary tie back anchors
through the Pier 5 Skewback footing into the canyon wall.
Crews on Pier 4 right erecting precast segments. The cableway
crane lowering the next segment for placement is visible. Temporary
scaffolding can been seen attached to Pier 3 left. Pier 2
is completed up to pier cap elevation. Behind pier 2, barely visible
is the scaffolding on Pier 1 and the partially constructed
Abutment 1.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from May 2006 |
|
Colorado River Bridge...
|

View of the excavation at Pier 14.
(looking down)Harris Rebar personnel placing
reinforcing steel for the Pier 14 footing (Arizona skewback).
Visible along the excavation walls are rock bolts installed to
provide slope stability.
High Resolution TIF (14 MB)
|

View of the formwork at Pier 14.
(looking down)Harris Rebar personnel placing
reinforcing steel for the Pier 14 footing (Arizona skewback).
High Resolution TIF (14 MB)
|

View of the excavation and formwork at Pier 14.
(looking east)View of the excavation and
formwork reinforcing steel placement for the Pier 14 footing
(Arizona skewback).
High Resolution TIF (14 MB)
|

The precast yard
(Boulder City, Nevada).
(looking west)Obayashi / PSM, JV nearing
completion of casting precast column segments at the precast yard
located near Boulder City, Nevada.
High Resolution TIF (14 MB)
|

Abutment 2
(looking northeast)View of the excavation and
formwork placement at Abutment 2.
High Resolution TIF (14 MB)
|

Abutment 2.
(looking down)Another view of the excavation
and formwork placement at Abutment 2.
High Resolution TIF (14 MB)
|

(overview - looking west)
High Resolution TIF (14 MB)
|

(zoomed in - looking west)
High Resolution TIF (14 MB) |
Lower Center: Olsen Beal erecting
precast segments to construct Pier 1 left.
Lower Center Background: Formwork can be seen for
Abutment 1.
Lower Foreground: Temporary scaffolding hangs from the
sides of Pier 2 Right and Left columns. This scaffolding is
utilized during segment erection and subsequent post tensioning
bar grouting operations.
|

Obayashi/PSM, JV Carpenters
(looking north)Obayashi / PSM, JV carpenters
constructing falsework / formwork for the cast-in-place pier caps.
High Resolution TIF (14 MB)
|

View of the bridge alignment
looking from Nevada to Arizona .
(looking northwest)View of the bridge
alignment looking at the Nevada approach spans. Depicted near the
center left are the partially constructed Abutment 1, completed Pier
1 right column, partially completed Pier 2 right, Pier 3, and Pier 4
right columns. At the lower center of this view is the completed
Pier 5 Skewback footing just below the existing US93 roadway
alignment.
High Resolution TIF (14 MB)
|

The future bridge alignment.
(looking east)View of the Colorado River
Bridge alignment looking from Nevada towards Arizona. Near the lower
left, the excavation for the future Pedestrian Plaza access trail
leading to Abutment 1 zigzags up from the future parking lot area .
High Resolution TIF (14 MB)
|

View of the bridge alignment
looking from Arizona to Nevada.
(looking east)Aerial view of the future
bridge alignment taken from Abutment 1 (Nevada) looking towards
Abutment 2 (Arizona). Shown at the bottom center of this picture is
the competed excavation for Pier 14 (Arizona skewback).
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from April 2006 |
|
Colorado River Bridge...
|

Rock Anchors in the backwall
(looking up)View of the installed rock
anchors of the excavated backwall of Pier 14 (Arizona Skewback)
taken from the footing elevation, looking up. The top of this ¼:1
excavated face is 146’ above the footing elevation.
At the right of this picture is the temporary ladder system in the
process of being constructed and bolted to the excavated wall.
High Resolution TIF (14 MB)
|

View of the bridge alignment looking towards Abutment 1 (Nevada).
(looking west)Lower Center: Formwork
and reinforcing steel of the Pier 5 Skewback footing.
Center: Erected precast segments of Piers 1, 2, and 3 right
columns in various stages of construction.
Upper Center: Formwork and reinforcing steel of partially
constructed Abutment 1.
Top: View of the cableway crane systems. The South cableway
(left) is completed while the North (right) is in the process of
being constructed. Visible to the left of the tower crane at the
lower center of the picture is the second 3” cable coming across the
canyon.
High Resolution TIF (14 MB)
|

Location for Abutment 2
(looking east)Rock excavation for Abutment 2 completed .
High Resolution TIF (14 MB)
|

Pier 5 Formwork
(looking southwest)Obayashi / PSM, JV
completing formwork for the Pier 5 Skewback footing.
High Resolution TIF (14 MB) |

Rock anchors at Pier 14
(looking down)View of the installed rock
anchors of the excavated faces of Pier 14 (Arizona Skewback).
Right: A temporary ladder system is in the process of being
constructed and bolted to the excavated wall to allow personnel
access to the footing.
Lower Left: Work crews take a lunch break and sit on the
excavation floor.
High Resolution TIF (14 MB)
|

Concrete Pump Trucks
(looking southwest)Obayashi / PSM, JV
utilizing two 58 meter pump trucks to place 2,030 cubic yards of
concrete, supplied by Casino Ready Mix, for the Pier 5 Skewback
footing. Placement operations were staged on the existing US-93 and
began at 6:30PM, finishing at 3:30PM the following afternoon.
High Resolution TIF (14 MB) |

Placing Concrete for Pier 5
(looking down)View of the concrete placement operation for
the Pier 5 Skewback footing.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from March 2006 |
|
Colorado River Bridge...
|

Preparing for the Lift
(looking south)Olsen Beal personnel rigging
the precast segment lifting jib onto a segment in preparation for
lifting it over the canyon for placement.
High Resolution TIF (14 MB)
|

Unloading
(looking south)View of a precast segment
being unloaded off of a transport trailer in Nevada near Abutment 1.
High Resolution TIF (14 MB) |

Towering Above
(looking west)Olsen Beal working on
construction of the North cableway crane in Nevada. These temporary
towers rise 330’ above the future roadway elevation.
High Resolution TIF (14 MB)
|

The Future Pedestrian Plaza
(looking northwest)Ladd & Associates
excavating for the Pedestrian Plaza access trail leading from the
future parking lot to Abutment 1.
High Resolution TIF (14 MB) |

Pier 5 formwork & reinforcing steel
(looking down)View of the Pier 5 Skewback
formwork and reinforcing steel looking down from the existing US-93
roadway elevation. The Colorado River flows approximately 650 feet
below the excavated ledge on which the Skewback footing is being
constructed.
High Resolution TIF (14 MB)
|

Building the North Cableway Crane
(looking west)Olsen Beal constructing the
North cableway crane in Arizona.
High Resolution TIF (14 MB) |

View of the bridge alignment looking
towards Abutment 1 (Nevada).
(looking southwest)Lower Center: Formwork and
reinforcing steel of the Pier 5 Skewback
footing in preparation for concrete placement.
Center: Olsen Beal erecting segments at Pier 2 right column.
Upper Center: Formwork and reinforcing steel of partially
constructed
Abutment 1.
Top: – View of the cableway crane systems.
High Resolution TIF (14 MB)
|
|
Return to the Top |
|
Images from February 2006 |
|
Colorado River Bridge...
|

Precast Pier
(looking southwest)Olsen Beal utilizing the
cableway crane to transport and lower a precast segment section for
Pier 3 right where it will be attached to the sections below.
High Resolution TIF (14 MB)
|

Cranes
(looking west)View of the roadway alignment
and two cableway cranes at Abutment 2 in Arizona.
High Resolution TIF (14 MB) |

Future Bridge Alignment
(looking east - towards Abutment 2; Arizona)
Lower Left: Ladd & Associates drilling holes for the tie back
anchors at Abutment 1. Behind the drill rig is the Abutment stem
wall under construction.
Lower Center: Visible below the tower crane are the stacked
precast pier segments for Pier 2 Right.
Upper Center Right: Completed excavation of Pier 14 (Arizona
Skewback). A Caterpillar 320C Trackhoe rests on the excavation
floor, approximately 600 feet above the waters of the Colorado River
below.
High Resolution TIF (14 MB)
|

Transporting precast pier sections
with the Cranes
(looking southwest)Top right: View of
the partially constructed Abutment 1.
Upper Center: View of the erected precast segments of Pier 2
right column. Visible to the right of this is the footing of Pier 2
left.
Lower Left: Olsen Beal utilizing the two cableway crane to
transport and lower a precast segment section for Pier 3 right.
Construction personnel stand on the footing of Pier 3 left viewing
the operation.
High Resolution TIF (14 MB) |

Over the River
(looking southeast)View of an 80 foot wide
preassembled reinforcing steel mat being transported across the
river by the cableway crane from the Abutment 2 area to the Pier 5
Skewback where it will be placed for construction of the footing.
High Resolution TIF (14 MB)
|

Placing the Reinforcing Steel Mat
(looking south)Paradise Steel personnel
direct an 80 foot wide preassembled reinforcing steel mat for Pier 5
footing into position as it is being lowered by the cableway crane.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from January 2006 |
|
Colorado River Bridge...
|

Future Bridge Alignment
(looking northwest)View of the bridge
alignment looking towards Abutment 1 (Nevada).
Lower Center: Footings of Pier 2 left and right.
Center: Stained Shotcrete constructed for stabilization of
the existing rock. To the left of the Shotcrete are the footings of
Pier 1 left and right.
Upper Left: The temporary towers of the cableway crane. Near
the bottom of these towers, reinforcing steel projects upwards for
Abutment 1.
High Resolution TIF (14 MB)
|

Obayashi/PSM, JV Constructing Formwork
(looking northwest)Overall view of Obayashi /
PSM, JV personnel constructing formwork for the footings of Pier 3
left and right.
Near the lower left, a shadow of a man basket appears on the canyon
wall. This picture was taken from this man basket as it was
suspended nearly 700 feet above the Colorado River by the Link Belt
TG1900 Tower Crane erected on Pier 4’s left foundation.
High Resolution TIF (14 MB) |

Constructing Formwork
(looking west)Obayashi / PSM, JV personnel
constructing formwork and reinforcing steel for the footings of Pier
3 left and right. Shown in the top left of this picture are rock
anchors installed in the excavation
walls.
High Resolution TIF (14 MB)
|

Constructing Formwork
(looking west)
Another photo of Obayashi / PSM, JV personnel constructing formwork
and reinforcing steel for the footings of Pier 3 left and right.
To the top left of this picture are the corrosion protection covers
of the installed rock anchors in the excavation walls.
High Resolution TIF (14 MB) |

Work on Piers 3 & 4
(looking down)Top Right: The Link Belt
TG1900 Tower Crane erected on the left footing foundation of Pier 4.
Lower Right: View the completed excavation for Pier 4 right.
Lower Left: Ladd & Associates utilizing a trackhoe to remove
fallen rock contained by a Rock Fall Containment system constructed
near Pier 4.
Upper Left: Obayashi / PSM, JV personnel constructing
formwork for the footings of Pier 3 left and right.
High Resolution TIF (14 MB)
|

View of the Bridge Alignment
(looking north)View of the bridge alignment
taken from downstream of Hoover Dam. Nevada approach appears to the
left with Arizona to the right. Visible near the top of this picture
is the twin 3” cables spanning the canyon for one of two cableway
cranes.
High Resolution TIF
(14 MB)
|

Excavation for Pier 5 Completed
(looking north)View the completed excavation
for Pier 5 (Nevada skewback). The excavated face shown is
approximately 100’ high. Corrosion protection covers of the
installed rock anchors in the excavation walls are visible in the
excavated rock face.
Hoover Dam appears near the lower left of the picture.
High Resolution TIF (14 MB)
|

Cableway Crane Tower
(looking south)View of the south Cableway
Crane tower in Arizona depicting the pull cable slack carriers,
hoist trolley, and tower stabilization cables.
High Resolution TIF (14 MB) |

Pulley System
(looking east)View of the twin 14 part pulley
system of the south Cableway Crane tower in Nevada. These pulleys
apply tension to the twin 3” highline cables that span the canyon.
High Resolution TIF (14 MB)
|

Skagit Hoist
(looking south)View of the Arizona Skagit
hoist used for erection of the Cableway Crane system.
High Resolution TIF (14 MB) |

Future Bridge Alignment
(looking west)View of the future bridge
alignment taken from Abutment 2 (Arizona) looking towards Abutment 1
(Nevada).
Foreground: The Link Belt TG1900 Tower Crane erected on the
left footing of Pier 15.
Background: Visible are the footings and excavations for
Abutment 1, Piers 1 through 5 (Nevada skewback), along with the Link
Belt TG1900 Tower Crane erected on the left footing of Pier 4.
High Resolution TIF (14 MB)
|

Olsen Beal Personnel
(looking south)Olsen Beal personnel winding
cable onto a temporary reel during the construction of the cableway
crane in Arizona.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from December 2005 |
|
Colorado River Bridge...
|

Future Bridge Alignment
(looking east)View of the bridge
alignment from Abutment 1 (Nevada) looking towards Abutment 2
(Arizona). Foreground: Obayashi / PSM, JV constructing
formwork and placing reinforcing steel for Abutment 1.
Background: Ongoing excavations for Pier 14 (Arizona
skewback) and Abutment 2 along with the towers of the temporary cableway crane.
High Resolution TIF (14 MB)
|

Nevada Approach Pier Excavations
(looking northwest)View of the bridge
alignment taken from downstream of Hoover Dam depicting the Nevada
approach pier excavations. The Link Belt TG1900 Tower Crane is
erected on Pier 4 left foundation.
High Resolution TIF (14 MB) |

Arizona Approach Pier Excavations
(looking northeast)View of the bridge
alignment taken from downstream of Hoover Dam depicting the Arizona
approach pier excavations. The Link Belt TG1900 Tower Crane is
erected on Pier 15 left foundation.
High Resolution TIF (14 MB)
|

Olsen Beal at work
(looking west)Olsen Beal constructing the
cableway crane in Arizona.
High Resolution TIF (14 MB) |

Stringing a line
(looking south)Upper right: View of
the helicopter transporting a half-inch cable across the canyon for
stringing of the cableway. Barely visible below the helicopter
is a hoop in the line used to grab once it reaches the Nevada side.
The second helicopter is being utilized as a spotter.
High Resolution TIF (14 MB)
|

Downstream of the Dam
(looking north)View of the bridge alignment
taken from downstream of Hoover Dam. Nevada approach appears
to the left with Arizona approach to the right. Visible near
the top of this picture is the twin 3" cables spanning the canyon
for one of two cableway cranes.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from November 2005 |
|
Colorado River Bridge...
|

Future Bridge Alignment
(looking east)View of the future bridge
alignment taken from Abutment 1 (Nevada) looking towards Abutment 2
(Arizona). Shown are the ongoing excavations for Pier 14 (Arizona
skewback) and Abutment 2. In the background of this picture,
are the towers of the temporary cableway crane which will span the
canyon and be utilized for construction of the bridge.
High Resolution TIF (14 MB)
|

Readying the Formwork
(looking east)Obayashi / PSM, JV personnel
ready column segment formwork in preparation for concrete placement.
Segments are wet cast against the next lower piece to assure a good
match cast joint.
High Resolution TIF (14 MB) |

Completed Precast Column Segments
(looking west)View of the completed precast
column segments stored and ready for shipment at the Obayashi / PSM,
JV precast yard located near Boulder City, Nevada.
High Resolution TIF (14 MB)
|

Excavation work continues
(looking west)Foreground: View of the
ongoing excavations for Pier 5 (Nevada Skewbasdk) and Pier 3, and
completed footings of Piers 1 and 2.
Background: The towers of the temporary
cableway crane which will span the canyon and be utilized for
construction of the bridge.
High Resolution TIF (14 MB) |

Excavations at the Arizona Skewback
(looking east)Foreground: Ladd &
Associates continuing excavation for Pier 14 (Arizona Skewback) and
Abutment 2 and installing rock containment fencing on the canyon
wall at Pier 14.
Background: The towers of the temporary
cableway crane which will span the canyon and be utilized for
construction of the bridge.
High Resolution TIF (14 MB)
|

Fine grading activities
(looking south)Ladd & Associates utilizing a
trackhoe and rock hammer to fine grade the excavation of Pier 5
(Nevada skewback). Bottom left in this picture is the rock
containment fencing installed on the canyon face.
High Resolution TIF (14 MB) |

Rock Anchors and a Temporary Ladder
(looking north)View of the installed rock
anchors of the north rock excavated face of Pier 5 (Nevada
Skewback). A temporary ladder system is in the process of
being bolted to this wall to allow personnel access to the footing
from the Nevada Hairpin area.
High Resolution TIF (14 MB)
|

Ladd & Associates continue grading activites
(looking down)Ladd & Associates utilizing a
trackhoe and rock hammer to fine grade the excavation of Pier 5
(Nevada skewback). Top left in this picture is the Colorado River,
approximately 650-feet below the level of this excavation. Top
right is a temporary rock containment structure.
High Resolution TIF (14 MB) |
|
Return to the Top |
|
Images from October 2005 |
|
Aerial Photos of the New US 93...
|

New Arizona Alignment
(looking west)Aerial view of the new
alignment in Arizona from Station 270+00 to 198+00 including the
interim US 93 roadway.
Foreground: View of the Arizona Interchange and associated
ramps, including the Sugarloaf Mountain TIOP Bridge.
Background: Sugarloaf Mountain Bridge.
High Resolution TIF (14 MB)
|

US 93 New Alignment
(looking north)Aerial view of the new
alignment from Station 63+00 to 123+00.
Bottom Left: Hoover Dam Canyon Bridge.
Top Right: Hoover Dam Lower Portal Access Road Overpass
(Structure H-2701), the Hoover Dam BOR Warehouse Old US 93 Overpass
(Structure H-2702), and the Hoover Dam Old US 93 Overpass (Structure
H-2703).
High Resolution TIF (14 MB) |

Nevada Interchange & Ramps
(looking north)Aerial view of the Nevada
Interchange and associated ramps, including the Hoover Dam
Interchange Bridge (Structure H-2699) and the Gold Strike Canyon
Access Road.
High Resolution TIF (14 MB)
|

Hoover Dam Canyon Bridge
(looking west)Aerial view of the new
alignment from Station 75+00 to 26+93.
Foreground: Hoover Dam Canyon Bridge (Structure H-2700).
Background: View of the Nevada Interchange and associated
ramps, including the Hoover Dam Interchange Bridge (Structure
H-2699) and the Gold Strike Canyon Access Road.
High Resolution TIF (14 MB) |

Aerial View of 3 new Overpasses
(looking west)Aerial view of the new
alignment from Station 123+00 to 71+00 including the Hoover Dam Old
US 93 Overpass (Structure H-2703), the Hoover Dam BOR Warehouse Old
US 93 Overpass (Structure H-2702), and the Hoover Dam Lower Portal
Access Road Overpass (Structure H-2701).
High Resolution TIF (14 MB)
|

The New Alignment tying into the OldAerial
view of the new alignment as it ties into the existing US 93 in
Nevada.
High Resolution TIF (14 MB) |
|
Colorado River Bridge...
|

Obayashi / PSM, JV Precast Yard
(looking east)Aerial view of the Obayashi / PSM, JV precast
yard located near Boulder City, Nevada. Four hundred-forty
(440) precast segments, each weighing approximately 35 tons, will be
constructed for the bridge approach and spandrel columns.
High Resolution TIF (14 MB)
|

Aerial View of Future Bridge AlignmentAerial view of the new alignment looking from Arizona towards
Nevada showing the location of the future Colorado River Bridge.
High Resolution TIF (14 MB) |

Aerial View of Future Bridge Alignment
(looking west)Aerial view of the future bridge alignment
taken from Abutment 2 (Arizona) looking towards Abutment 1 (Nevada).
Shown are the ongoing excavations for Pier 5 (Nevada skewback) and
Pier 3, and completed footings of Piers 1 and 2 along with the
excavation for Abutment 1 footing.
High Resolution TIF (14 MB)
|

Excavations for Pier 14 & Abutment 2
(looking east)Aerial view of the future bridge alignment
taken from Abutment 1 (Nevada) looking towards Abutment 2 (Arizona).
Shown are the ongoing excavations for Pier 14 (Arizona Skewback) and
Abutmen |